Resolved that – (i) the revised position of the 2006/07 Cityfocus Delivery Plan as submitted be approved; (ii) the capital programme of the City Council be amended to reflect increased expenditure of £77,254 of SRB projects and SRB grant bringing the total capital expenditure to £2,072,402 as detailed in Annex 1 submitted; (iii) the revenue budget of the City Council be amended to reflect reduced SRB expenditure and SRB grant of £106,808 as detailed in Annex 1 submitted; (iv) subject to prior approval by the Cityfocus Board and consultation with the Executive Member for Special Initiatives and with the Executive Member for Resources, the Interim Executive Director (Regeneration) and the Executive Director (Finance and Legal Services) be authorised to approve new projects and to vire SRB grant between projects and between the Revenue and Capital programmes within the SRB/SIA Programme in the last quarter of the financial year 2006/7 in order to commit expenditure and achieve programme outputs or respond to specific needs; and (v) authority be given to commit the expenditure. RES/46
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek approval to the adjustments to the agreed 2006/07 Cityfocus Delivery Plan in order to ensure the full implementation of the Programme and to amend the City Council’s Capital Programme accordingly.
Background 1. On 31st March the Executive Board approved the Cityfocus Delivery Plan for 2006/07. This was formally approved by NWDA on 17th May 2006. The Delivery Plan detailed the projects and the expected levels of investment in the year. The financial breakdown was £1,995,148 capital and £2,017,111 revenue in 2006/7 to reflect the proposed allocation and spend of SRB resources. The expenditure is 100% SRB grant funded.
2. During the course of the year the Cityfocus Board has reviewed regularly both the performance of the approved programme and the individual projects within the programme. The primary focus of this review is on ensuring that the programme is fully implemented in accordance with the approved Plan. This includes taking any corrective action which may be necessary and making appropriate adjustments to ensure the full delivery of the approved programme.
Current Position
3. Annex 1 details the amendments required to the City Council’s capital and revenue programmes to reflect the necessary changes to the SRB programme. The main changes in capital expenditure from the approved Delivery Plan are: Cruise Liner Facility –Construction - carry over of £122,580 SRB grant from 2005/06 reflecting the delayed start on site Townscape Heritage Initiative - reduction of £34,383 SRB grant because of the slow take up of individual grants in the first two quarters of the financial year 2006/07; Supporting Biotechnology Business Incubation – the project is now complete and the remaining £30,000 SRB grant is no longer required; Buddleia Project - reduction in the allocation for 2006/07 because the progress on site was quicker than anticipated enabling £280,000 SRB funding to be brought forward and spent in 2005/06; Feature Lighting Phase 2 - the release of £200,000 in 2006/7 to complete the full funding package agreed by NWDA and ensure the delivery of the approved programme. 4. The Cityfocus Board will continue to monitor the programme closely to ensure the programme targets and outputs are fully met.
Executive Members/Interim Executive Director recommendation (Councillors Mike Storey CBE and Keith Turner/Ben Dolan):
Recommendation that: 1) The revised position of the 2006/07 Cityfocus Delivery Plan be approved;
2) The capital programme of the City Council be amended to reflect increased expenditure of £77,254 of SRB projects and SRB grant bringing the total capital expenditure to £2,072,402 as detailed in Annex 1;
3) The revenue budget of the City Council be amended to reflect reduced SRB expenditure and SRB grant of £106,808 as detailed in Annex 1;
4) Subject to prior approval by the Cityfocus Board and consultation with the Executive Member for Special Initiatives (as required by the Council’s Constitution) and with the Executive Member for Resources, the Interim Executive Director (Regeneration) and the Executive Director (Resources) be authorised to approve new projects and to vire SRB grant between projects and between the Revenue and Capital programmes within the SRB/SIA Programme in the last quarter of the financial year 2006/7 in order to commit expenditure and achieve programme outputs or respond to specific needs; and
5) Authority be given to commit the expenditure.
Key Decision: Yes Forward Plan : Yes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.