Resolved that - (i) Professor Bonsall’s reports in relation to the review of the City Centre Movement Strategy be noted. (ii) the proposed responses to Professor Bonsall’s reports be approved and, in particular, that – · discussions be undertaken with Merseytravel with a view to setting up procedures for the assessment and analysis of options for the continuing development of the highway and transport networks and to report thereon; · proposals for bus layover in the city centre be progressed; · a scheme for alterations to the junction of Tithebarn Street and Bixteth Street be progressed and further approvals sought as necessary; and · proposals for camera enforcement of bus lanes including for minor works to improve clarity of the approach to the north-bound bus lane on Lime Street be progressed; and (iii) the decision, together with the technical reports produced by Professor Bonsall , be referred to the City Centre Movement Strategy Scrutiny Panel of the Regeneration and Economic Development Select Committee. NH/14
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The City Centre Movement Strategy (CCMS) was defined, and its objectives set, by the first Local Transport Plan (LTP) 2001-6. CCMS also meets defined objectives set out in the Regional Economic Strategy and Liverpool Vision’s Strategic Regeneration Framework.
A substantial part of the Strategy has been successfully implemented over its first 5 years, the majority of the works completed on time and to budget, and the work has won a number of major awards including the National Transport Award for Walking and Public Realm in 2005.
CCMS remains a key priority within LTP2 but the Executive Member for Regeneration thought it appropriate to carry out a review at the start of the period of this LTP, particularly in the light of the uncertainty surrounding Merseytram which formed an integral part of the overall CCMS. This would determine whether the projects implemented met the key objectives of the strategy.
In addition the Executive Member had carried out a number of site inspections with officers and highlighted a number of areas where it was considered prudent to test the effectiveness of the measures introduced. . 2 Critical Review
2.1It was determined that a review should be carried out by a “critical friend” who could assess the Strategy against its original objectives.
2.2Peter Bonsall is the Professor of Transport Planning at the Leeds Institute of Transport at Leeds University. He accepted a commission to: Review the City Centre Movement Strategy with particular reference to the concerns which have been raised about its appropriateness in the light of the indefinite delay to the implementation of the LRT scheme (ie Merseytram) which formed a component of the original strategy
He was asked to concentrate on strategic issues and was not initially asked to undertake detailed traffic analysis or audit specific engineering designs. He was, however, later asked to produce a second report into some matters of detail.
3 The Report
3.1Professor Bonsall’s report is appended. It is not summarised here as it is concise and to the point. However the conclusions and recommendations are stated or summarised here, together with comment as appropriate.
3.2In response to some concerns about the operation of the network Professor Bonsall was later asked to produce a more detailed report. This looked at congestion issues on the recently completed Tithebarn Street Improvement, The Adelphi Interchange and at Seymour Street. This is also appended.
4 Discussion of the main report’s conclusions
4.1Conclusion “I see no reason to challenge the objectives of the CCMS or to disagree with its aim to remove extraneous traffic from the City Centre or to improve accessibility by bus and on foot. Any modification of the existing plans should be judged against these objectives”.
LCC Comment This conclusion is accepted.
4.2Conclusion “… it would be advisable to revisit the question of the likely performance of the Liverpool road network in the presence of the additional demand associated with new developments but in the absence of an LRT” (ie Merseytram)
LCC Comment This conclusion is accepted. It is recommended that officers from the Regeneration Portfolio meet with Merseytravel, who also have a significant role in the performance and management of the transport network, to decide how best to provide this assessment and to report further.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.