Objective 1 – Liverpool Neighbourhood Regeneration Programme – Further Commissioning Exercise Final (EDE/14)

Approved Executive 1 paper

Executive Board approved this item on Friday 7 December 2007. Below is the council's own wording, with the papers it was decided on.

Item109h

Resolved

Resolved that – (i) Liverpool City Council on behalf of the Liverpool First, the Local Strategic Partnership, commit the sums submitted as grant awards to Kirkdale Neighbourhood Council as recommended by LNRPG; (ii) revenue income and expenditure budget of the Regeneration Portfolio be reduced by £150,000 in 2007/08 and by £350,000 in 2008/09; (iii) the capital programme be amended to include the capital schemes listed in the Financial Implications section of the report submitted in the Regeneration capital programme to the total sum of £500,000 with expenditure of £150,000 in 2007/08 and £350,000 in 2008/09 with financing from ERDF grant income; (iv) authority be granted to the Executive Director (Regeneration), in consultation with the Executive Members (Economic Development & Europe) and (Resources) to approve the reallocation of grant and issue relevant amended offer letters on behalf of the Liverpool First, the Local Strategic Partnership, to those projects highlighted at Appendix 3 submitted to increase the amount of grant awarded as and when unspent resource becomes available and make the identified alteration to the Capital Programme at the relevant point in time; and (v) further monitoring reports regarding project delivery be submitted in due course. EDE/16
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 13 pages

Executive summary

The Executive Board have approved a number of reports outlining the development and delivery of a new approach to the investment of Objective 1 funds in deprived communities. These reports have culminated in Liverpool City Council taking on accountable body status for some £34.5 million of Objective 1 funding on behalf of Liverpool First to establish and deliver the Liverpool Neighbourhood Regeneration Programme (LNRP). A List of Preferred Provider organisations has been established to deliver key regeneration activities on behalf of Liverpool First. This exercise has ensured that any organisations that deliver an element of the programme meet minimum quality standards in terms of financial accountability, equal opportunities, health and safety and track record of delivery. The list includes a range of organisations including LCC Portfolios.

The Liverpool Neighbourhood Regeneration Programme Group (LNRPG) is the Liverpool First sub committee that has the strategic direction and overview of the Liverpool Neighbourhood Regeneration Programme. As part of this process they, in conjunction with the local Cluster Boards and Neighbourhood Management Teams, have decided to commission the following activity: • Liverpool Atlantic Kirkdale Recreation Ground

That activity has been tendered to relevant organisations on the List of Preferred Providers.

This report: • advises Members on the responses received to the grant award process • requests members to approve the most appropriate proposal received based upon the agreed technical and strategic appraisal processes • requests members to make the relevant amendments to the Capital Programme.

The grant process and technical and strategic appraisal processes accord with Liverpool City Council policies and the grant funding guidelines for Objective 1 agreed with Government Office North West and national Government. Approval of this project will mean the Liverpool Neighbourhood Regeneration Programme is now fully committed. All relevant projects will now need to be delivered and completed by no later than October 2008 in order to allow the Council to make its final claim to GONW.

As with many time limited grant programmes however there is always the danger that individual projects may underspend. Earlier during the LNRP process this would have been accommodated by commissioning further activity however given the short timescales now left in the programme it will be impractical to commission any new provision.

On that basis Section 4 outlines the work carried out to establish a list of reserve activity which can be utilised to soak up underspend as and when grant becomes available.

This report therefore also requests members: • to approve the list of reserve activity for award of grant as and when underspend becomes available.

1. Establishing the Tender Requirements

Need for Investment

The Merseyside Objective 1 Programme has identified a range of areas across the sub-region as the most deprived communities requiring additional investment. To that end an allocation of Objective 1 resource has been made available to these areas through the Liverpool Neighbourhood Regeneration Programme for investment in key local priorities. The activities covered in this report will be funded from that allocation.

The need for these specific investments has been identified by the relevant Cluster Boards and based upon the needs identified in the Neighbourhood Action Plans and Neighbourhood Delivery Plans.

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Objective 1: Liverpool Neighbourhood Regeneration Programme: Further Commissioning Exercise Final (EDE/14)Report 13 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
CE
Councillor Colin EldridgeMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, apologies
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
TH
Tony HunterOfficer, present

All 18 on the meeting page

On this subject at Liverpool

Search all
  1. Objective 1 – Liverpool Neighbourhood Regeneration Programme – Further Commissioning Exercise Final (EDE/14)This decision
  2. Liverpool City Council’s Equality Objectives 2020-2024 (CP/8)Decided
  3. Liverpool City Council Equality Objectives 2016-20 (FSE/3)Approved
  4. Objective 1 – Liverpool Neighbourhood Regeneration Programme – Further Commissioning Exercise 4 (EDE/4)Agreed
  5. Objective 1 – Liverpool Neighbourhood Regeneration Programme – Further Commissioning Exercise 3 (R&T/74)Decided
  6. Objective 1 Liverpool Neighbourhood Regeneration Programme (R&T/54)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open