Resolved that – (i) progress to date in relation to the Speke District Centre, be noted; (ii) the City Council’s Regeneration Capital programme be amended to reflect the expenditure detailed below, to be funded from the Morrisons ’ Capital Receipt in 2007/08 - · compensation payments £1,200,000; · demolition of existing District Centre and clearance of site £2,500,000 with Liverpool Land Development Company (LLDC) to be put in funds to carry out the work on behalf of the City Council; · legal and technical fees £293,757 incurred by LLDC during the delivery of the project; · Education Solutions PFI payment £1,200,000 **; and · contingency sum of £98,000 to include provision for additional security and repair work on the existing District Centre prior to demolition; (iii) the remaining receipt £ 3,242,120 will contribute towards the City Council capital receipts target; and (iv) authority be granted to enter a deed of variation to the original PFI contract with Education Solutions to reflect the 12 month extension required. (** Payment is due under the terms of the Speke forward learning centre contract between Education Solutions Speke Ltd and Liverpool City Council dated June 2001) REG/38
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
To inform Executive Board of the latest position regarding the development of a new replacement shopping facility at Speke District Centre to serve the Speke Estate to agree amendments to the City Council Capital Programme and other recommendations in support of delivery of the project.
Background
2.1Liverpool Land Development Company is spearheading the physical and economic regeneration of the four non-City Centre Strategic Investment Areas. As part of that, the Company is co-ordinating the delivery of this project on behalf of the City Council.
2.2In June 2002, the City Council provisionally agreed terms for the disposal of land between the Parklands Centre and Speke Boulevard (“the Site”) to Wm. Morrison Supermarkets plc (“Morrison”) for the purpose of developing a new replacement retail facility to serve the Speke Estate. LLDC acting as agent on behalf of the Council negotiated the terms and prepared an appropriate conditional Development Agreement for disposal of the site. 2.3. The Development Agreement was subsequently entered into in April 2003, and led to the transfer of the freehold of the Site to Morrison on March 2007 having met the conditions set out below.
3. Development agreement conditions
3.1Supplemental Agreement - Education Solutions
3.1.1. The City Council is required to enter into a Supplemental Agreement to the Principal Agreement with Education Solutions Speke Ltd in relation to part of the land comprising the Speke Forward Learning Centre (now Parklands) PFI scheme.
3.1.2. This Agreement was exchanged in June 2004 on a conditional basis; the condition which needed to be satisfied, before the terms of this Agreement are effective is for all of the remaining conditions under the Principal Development Agreement with Morrison to be satisfied. This has now been confirmed.
3.1.3. This Agreement amends the boundaries of the Forward Learning Centre to accommodate the Morrison scheme. It will also allow Morrison to undertake works to a paved area within the curtilage of the Forward Learning Centre and give Morrison maintenance responsibility of the road into the site from Ganworth Road, with Education Solutions and the Forward Learning Centre occupiers being given rights of access.
3.2A Satisfactory Planning Consent being granted
Detailed planning consent was granted on 20th January 2005, subject to certain conditions. Following the issue of a Revised Approval Notice on 14th June 2005 Morrison confirmed that, in its view, this constituted a Satisfactory Planning Consent for the purposes of the Development Agreement.
3.3Agreement with BEP (Speke) Ltd
3.3.1. The terms of the Agreement with BEP (Speke) Ltd, the former long leaseholder of the existing District Centre, have been agreed and the Agreement, to which Morrison were a party, was exchanged on 3rd October 2005. As provided for in this Agreement, Morrison acquired the Head leasehold interest(s) from BEP and retained interests until such time as the completion date under the Principal Agreement between LCC and Morrison to enable the transfer of the main site had completed. This occurred 8 March 2007
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.