Resolved that – (i) the Half Year Financial Review 2008-09 and the Medium Term Financial Plan update, be noted; and (ii) the best thanks of the Board be extended to the Officers and Members for all the hard work undertaken in relation to this matter.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This review is the assessment of the financial position of the Council as at the end of September 2008. It is an exception report highlighting significant movements from the agreed 2008/09 budget.
2008/09 Budget Decisions
• The majority of the budget decisions are on track to deliver the required financial affects. However, there are two specific decisions in adult services and one relating to highways which are now forecast as unlikely to deliver their budget saving – totalling £1.180m. As such part of a contingency will now need to be set aside to offset the implications.
• The issues identified as risks and uncertainties at the time the budget for 2008/09 was prepared are expected overall to be contained within established provisions and reserves.
• The Council has received a number of grievances relating to the implementation of the Council’s pay protection policy and the payment of part time staff which could result in additional costs.
Additional Cost Pressures
• Portfolios are, identifying a range of issues which may increase costs. These issues represent a risk to the Council improving its working balances and financial standing.
• Portfolios have identified and are taking the appropriate actions that will produce offsetting savings. As some of the issues are ongoing then the offsetting actions will need to involve real reductions in costs on an ongoing basis.
• The budget for 2008/09 relied upon £3m of works and costs being eligible to be funded from capital receipts. The downturn in the national and local economy has resulted in the volume and the value of sales being significantly reduced. As such it is prudent to now anticipate that no more than approximately £1.5m of eligible costs will be able to be funded as intended.
• The budget for 2008/09 anticipated that there would be certain one-off costs to be incurred to achieve a number of the budget decisions and therefore a service delivery provision was established. Whilst the majority of those costs have avoided through pro-active management of the re-deployment procedures specific service areas are incurring costs. However, whilst the total of such costs has yet to be finalised it is estimated that those costs will be able to be contained well within the available provision. • The Council is also challenging two potential grant claw-back situations relating to the capital financing of the Kings Dock development. If unsuccessful the cost would be funded from available grant claw-back reserve.
2007/08 Accounts
• The accounts for 2007/08 have now been audited and there were no adjustments to the financial position arising from the audit.
Summary of the implications on the 2008/09 Budget
• The table below summaries the current position.
Best Case Worst Case £m £m 2008/09 Budget Decisions Supported accommodation & care services efficiency reviews 0.1 1.0 Street lighting advertising income 0.3 0.3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.