Resolved that – (i) authority be granted for the Executive Director (Regeneration) to accept additional grants from the NWDA up to a maximum of £1,183,000 (from £871,000, i.e. an increase of £311,910 over previous authorisation); (ii) the Team Leader (Highways Projects Team in the Transportation Service) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iii) authority be given to the Assistant Executive Director (Planning and Transportation) to negotiate an increased target cost sum of up to £852,657 (from £582,872, i.e. an increase of £269,785) with consultant 2020Liverpool in respect of design and supervision fees; (iv) an increased estimated outturn to £1,972,637.24 (from £1,623,308.00 i.e. an increase of £349,329.24) with contractor Aggregate Industries in respect of construction work, be approved; and . (v) authority be granted to commit expenditure. A&D/45
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Purpose of this report 1.1 This report seeks Executive Board approval to increases in the available funding for the Castle Street Enabling Works and authority to pay the contractor for additional works.
2. Background 2.1 The construction of the Castle Street Enabling Works is now complete, subject to any remedial works. The project, designed and supervised by 2020 Liverpool and constructed by contractor Aggregate Industries, involved work on many prominent streets in the core central area: Lord Street, North John Street, Dale Street, Victoria Street, Cook Street which were required to be co-ordinated with other construction activity in and around the city centre.
2.2Despite this and the additional works detailed in this report, the project was completed on schedule and with all disruption well managed; the efforts of consultant and contractor in achieving this are appreciated.
2.3On 26th October 2007 (min. 88h refers), the Executive Board gave approval for the Council to accept external funding for the Castle Street Corridor and Enabling Works, together with authorisation for payments to be made to the contractor up to a limit of £1.623 million.
2.4However, the extent of construction was extended because of the inclusion of additional works into the contract, funded from a variety of public and private sector sources as described in the report below. As a consequence, the maximum sum payable to the contractor has increased, such that the original financial limit has now been exceeded. 2.5 This report therefore seeks Executive Board approval to the increases in the available funding, [which are already approved in the Capital Programme] and to increase the maximum payment that can be made to the contractor to cover the additional works.
3. Reasons for extensions to the works
3.1The value of the original construction contract was extended to take advantage of additional external funding which became available, generally at very short notice, and enhancements to the scheme as a result of complementary works, funded from other Council budgets.
3.2These additional construction works were as follows (the second column indicates where funding for the particular area of increase is taken from):
Event Funded from To provide increased areas of paving in natural NWDA materials on North John Street when additional funding became available from NWDA To allow the timely removal of the footbridge across LTP (2007/08) The Strand which would otherwise have been Grosvenor (private postponed until 2009 sector contribution) NWDA To lay new road surfacing on North John Street Highways Maintenance Revenue (2007/08) transferred out To make amendments to the Vernon LTP CCMS (2008/09) Street/Tithebarn Street junction following a road safety audit of these earlier works To provide additional CCTV cameras for Citywatch Citywatch (2007/08) transferred out
3.3In addition to the above, there were supplementary design and supervision fees due to 2020Liverpool.
3.4These works were additional to the main contract and therefore there are no savings to the City Council’s contribution to the project.
4. Financial Consequences
4.1The anticipated final scheme costs are as follows:- Anticipated Outturn Costs Project Castle St Enabling Works (Package 2A) Period 25th September 2008 Current Status Anticipated Outturn Costs Anticipated Item Original Approval Outturn Difference £ £ £
Contractor Costs Base Construction Cost 1,623,308.00 1,637,882.01 14,574.01 Additional Events 0 334,755.23 334,755.23 Total Construction Costs 1,623,308.00 1,972,637.24 349,329.24
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.