Resolved
Resolved that subject to the above amendments the recommendation be approved. SSC/25
Executive Board approved this item on Friday 21 November 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that subject to the above amendments the recommendation be approved. SSC/25
Purpose of the Report This report seeks approval for the funding of the Stanley Street, Cumberland Street and Eberle Street Scheme and to amend the capital programme.
Background to the proposal On 18th October 2006, the City Council considered a motion proposing the closure of Stanley Street between the minor streets, Davies Street and Progress Place, that run behind properties on Stanley Street. There were also requests to close Eberle Street and Cumberland Street. The City Council agreed to initiate consultation exercise with a view to implementing pedestrianisation of the northern section of Stanley Street. The aim of the motion was to assist the night time economy in this section of the city, by encouraging greater pedestrian activity and comfort. The proposals would also assist in achieving the CCMS objectives and would meet the aim of improving city centre north to south links for pedestrians. After investigation, Members were advised in December 2006 that the motion, as proposed, was not practical due to a lack of suitable alternative servicing of Stanley Street properties. Scheme proposal An alternative scheme was therefore developed which achieved the overall objective of the City Council motion (i.e. namely to improve the night time economy, whilst at the same time permitting access during daytime for local businesses). This is achieved by prohibiting traffic after a certain time in the evening from entering these streets. The alternative scheme proposed that hydraulic bollards would be raised between 6pm and 6am on seven days per week on Stanley Street and Cumberland Street. Eberle Street would be closed for 24 hours every day, as it is technically, but not practically, at present. Persons needing night-time access to off-street car parking served by any of the streets would be issued with proximity cards that automatically lower the bollard. The usual exemptions to the TRO (e.g. the emergency services and highway maintenance vehicles) would apply. A similar arrangement currently operates in the Cavern Quarter nearby. Night-time removal of traffic would apply to the full extent of the proposals. This would improve the local environment during the streets’ busiest time and assist night-time pedestrian activity and economy. The scheme offered for consultation was the installation of automatic rising bollards at the entrance of the three streets as indicated below: • Stanley Street – Three number rising bollards • Cumberland Street – Two number rising bollards • Eberle Street – Two number rising bollards In addition fixed bollards, of a suitable design, would also be provided as necessary in the footway to prevent vehicles mounting the pavement to by-pass the rising bollards once in operation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanley Street, Cumberland Street and Eberle Street Scheme (A&D/46)Report | 9 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.