Resolved
Resolved that the recommendation be approved. EDCS/22
Cabinet 2010/21 approved this item on Friday 8 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved. EDCS/22
The Rhys Jones Memorial Fund (RJMF) have progressed a scheme to develop a new sporting and leisure facility on land at Langley Close in Croxteth, which has the benefit of planning permission. As the major stakeholder in the scheme it has been agreed that the Council will take over the delivery of the project including the transfer of monies raised by the Trust to the Council. To speed up delivery it is further proposed that Regeneration Liverpool (the Council’s Asset Backed Vehicle) take on responsibility for the design and build of the building, with the aim of having the facility open by July 2013.
1.1Following the tragic shooting of Rhys Jones a Trust was established (the Rhys Jones Memorial Fund) with the aim to raise funds to deliver a “sporting and leisure community centre for the residents of Croxteth Country Park and surrounding area.”
1.2The Trust to date has raised £255,000 in support of its aims, which has seen a scaling back from the original proposal for the facility (with an original cost estimate of circa.£1.6m) to one which is in line with the current available budget.
1.3In respect of this the Council has also committed, at an Executive Board meeting on 18 January 2008, to contribute £250,600 to support the initiative. It has further agreed to make its land available at Langley Close for the proposed new centre. 2. Proposed Centre
2.1Planning permission was granted on 30 October 2012 to the Rhys Jones Memorial Fund to build a small community centre and two all weather pitches on the existing greenspace at Langley Close. Details of the indicative layout of the facility are attached, which will include:-
• a community building with sports changing facilities, toilet facilities, a small kitchen and a multi function, community room in a modern, single storey building;
• parking next to the community building for 16 cars; and
• enclosed floodlit seven-aside 3G pitches.
2.2The scheme and cost plan, which have been prepared by Falconer Hall and Tweeds, on behalf of the Trust have been appraised by 2020 Liverpool and they have advised that the scheme can be delivered within the available budget of £505,600.
3 Delivery Arrangements
3.1The Council has provided support and assistance to the Trust and the various stakeholders in bringing this project forward. It has been agreed between the parties that as the major stakeholder in the project (in terms of funding and land ownership) that the Council will take on responsibility for the construction of the centre and finalise the management arrangements of the facility.
3.2This will include, subject to the approval of the Charity Commission, the Trust transferring the funds it has raised to the Council. The Trust have applied to the Charity Commission for the funds to be transferred to the Council and are awaiting confirmation to this.
3.3To expedite the physical delivery of the scheme it is proposed that the design and build of the centre is procured through Regeneration Liverpool (the Council’s asset backed vehicle). This would entail the Council granting a building licence to Regeneration Liverpool to build the facility which it would undertake through its affiliate arrangement with Neptune, who have already been heavily involved in the project since its inception in 2007. The Trust have already progressed the scheme to tendering for the works. Neptune will effectively take over from the Trust and finalise the arrangements for the appointment of the contractor.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
The Rhys Jones Sport Pitches (R/25)Report | 8 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.