Cabinet 2010/21, Friday 8 March 2013

Liverpool - A Strategic Housing Delivery Partnership (H/16)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 8 March 2013. Below is the council's own wording, with the papers it was decided on.

Item126d

Resolved

Resolved that the recommendation be approved. TCC/10
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 6 pages

MAYORAL RECOMMENDATION

CITY STATUS – PUBLIC H/16

Cabinet Member: Director: Councillor Ann O’Byrne Nick Kavanagh, Cabinet Member - Housing Director – Regeneration and Employment

Date of submission: Subject: 8th March 2013 Liverpool – A Strategic Housing Delivery Partnership

Report No./Background papers: Contact Officer: ER/06/13 Jayne Traverse Divisional Manager – South, (Tel:233 2532)

Executive Summary: The Mayor of Liverpool has set in progress arrangements to deliver his Mayoral targets including constructing 5,000 new homes, bringing 1000 homes back into use and making the city cleaner, greener and healthier.

In response to growing interest from the market to support the delivery of the Mayors targets of new and refurbished homes across the City, this report outlines plans to seek one or more lead housing delivery partners to contribute 1,500 towards the Mayors new homes Pledge as well as bringing 1,000 homes back into use.

Background: Cabinet will recall approving reports detailing the Council’s ambitious city wide plans for Housing Delivery, incorporating both new build and refurbishment programmes, which will support the delivery of the Mayor’s targets.

The City Council is leading and or facilitating the delivery of these new and improved homes, including tackling some of our most challenging areas hit hardest by economic recession. We are achieving this through a number of groundbreaking initiatives working with our public and private sector partners and in many cases these are contributing to wider, comprehensive and integrated regeneration projects.

Programmes of activity are underway already to deliver in excess of 5200 new and 1100 refurbished houses across the City. In addition to creating new and or better homes the projects will stimulate activity in the construction industry and lead to employment and apprenticeship opportunities.

There are currently 31 live development sites across the city delivering over 2000 new homes.

There has also been a growing interest of late from potential investors, Registered Providers, the third sector and developers, who want to support the delivery of new and refurbished housing across the City. The proposals contained in this report are in response to that interest from the market.

Proposal: In order to maximise investment potential in Liverpool and support sustainable housing growth it is considered that the appointment of one or more public or private sector housing delivery partners will be key. They would work alongside our existing partnership arrangements, to deliver a minimum of 1500 new homes and up to 1000 refurbished homes in a first wave of activity.

Our current Housing Delivery Programme includes -

• Housing Delivery Plan (a consortium of Registered Providers on City Council sites); 1000 new homes;

• Housing Renewal Programme (continuation of delivery of new homes in the former HMR areas); 1880 new homes;

• Regeneration Liverpool (work in collaboration with the Councils Asset backed Vehicle); 1500 new homes;

• Schools Investment Plan (sale of Council owned sites to housing developers); 880 new homes;

• Other Programmes (a mixture of public and private sector led schemes across the city); 1600 new homes; and

• Clusters of Empty Homes (recently announced £14Million award for Liverpool for Liverpool City Council in collaboration with partners); 676 Refurbished Houses.

The partnership could also potentially lead to a second wave of wider regeneration activity, to include non housing related development projects.

The procurement exercise will be carried out through the quickest possible OJEU procedure by which to test the market and appoint a partner or partners. The process will involve a Prior Indicative Notice (PIN) to warm up the market, open/bidders days, which will include an opportunity to promote the City to a national and indeed international audience.

The bid assessment will include the following:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Liverpool: A Strategic Housing Delivery Partnership (H/16)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Liverpool - A Strategic Housing Delivery Partnership (H/16)This decision
  2. Liverpool Strategic Highway Network Investment (TCC/12)Approved
  3. Presentation - The Strategic Direction of Liverpool Adult Learning ServiceAgreed
  4. Liverpool City Centre Strategic Investment Framework 2012 - Emerging Priorities & Next Steps for Delivery (M/8)Approved
  5. Liverpool Climate Change Strategic Framework and Liverpool Climate Change Adaptation FrameworkAgreed
  6. Hall Lane Strategic Gateway Scheme and Royal Liverpool University Hospital Redevelopment (A&D/6)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies