Capital Programme Monitor 2013/14 - Month 9 (December 2013)

Agreed Executive 6 papers

Cabinet 2010/21 agreed this item on Friday 21 February 2014. Below is the council's own wording, with the papers it was decided on.

Item271a

Resolved

Resolved that Cabinet – (i) agree the Period 09 budget net decrease of £24.914m, to the latest 2013/14 capital programme already approved by Cabinet, as included in Table 1 / Annex 1 (summary) to the report submitted, to produce a revised programme of £178.007m; (ii) approve the capital budgets of £178.007m for 2013/14, £218.086m for 2014/15, £74.822m for 2015/16, £51.213m for 2016/17 and £24.410m for 2017/18 as detailed in Tables 2, 3 and 4 of the report submitted. These sums update those included in the City Council Capital Strategy document for 2013/14 – 2017/18 (DRFC14/13) presented to Cabinet on the 22 February and Full Council on 6 March 2013; (iii) note spend to date of £100.726m, representing a 56.6% of the revised total capital budget for 2013/14, as set out in Annex 1 to the report submitted, with 75.0% of the year having elapsed, and an anticipated projected spend of approximately £178.007m; (iv) note that actual spend is showing a 13.7% shortfall against the budgeted profile. This represents a monetary value of £15.848m on a total 2013/14 Programme of £178.007m. This shortfall will need concerted managerial action and close monitoring if the reported forecast is to be maintained; (v) note the position regarding the prudential indicators approved as part of the Treasury Strategy Report 2013/14, presented to Council 6 March 2013; and (vi) note the total level of Council Borrowing of £435m (£345m borrowing and £90m Other Long Term Liabilities) as at 31 December 2013.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 13 pages

Recommendations

Members are asked to:

A. Agree the Period 09 budget net decrease of £24.914m, to the latest 2013/14 capital programme already approved by Cabinet, as included in Table 1 / Annex 1 (summary), to produce a revised programme of £178.007m.

B. Approve the capital budgets of £178.007m for 2013/14, £218.086m for 2014/15, £74.822m for 2015/16, £51.213m for 2016/17 and £24.410m for 2017/18 as detailed in Tables 2, 3 and 4. These sums update those included in the City Council Capital Strategy document for 2013/14 – 2017/18 (DRFC14/13) presented to Cabinet on the 22nd February and Full Council on the 6th March 2013.

C. Note spend to date of £100.726m, representing a 56.6% of the revised total capital budget for 2013/14 (Annex 1), with 75.0% of the year having elapsed, and an anticipated projected spend of approximately £178.007m.

D. Note that actual spend is showing a 13.7% shortfall against the budgeted profile. This represents a monetary value of £15.848m on a total 2013/14 Programme of £178.007m. This shortfall will need concerted managerial action and close monitoring if the reported forecast is to be maintained.

E. Note the position regarding the prudential indicators approved as part of the Treasury Strategy Report 2013/14, presented to Council 6th March 2013. F. Note the total level of Council Borrowing of £435m (£345m borrowing and £90m Other Long Term Liabilities) as at 31st December 2013.

Background

3.1The capital programme monitors are produced each month of the financial year with an outturn report in June. The Capital Strategy 2012/13 to 2016/17 report was approved by Council 7th March 2012. This included indicative allocations of capital grants for 2012/13 to 2016/17. This has been superseded by the Capital Strategy 2013/14 – 2017/18 (DFR14/13) report and the Capital Programme 2013/14 – 2017/18 report (DFR09/13) approved by Cabinet of 22nd February 2013 and Full Council 6th March 2013

3.2The Council’s capital programme is subject to monthly review by a senior group of officers. Under a banner of the Capital Programme Group each new project will be scrutinised under a new “gateway process” to be confirmed as follows:

• Project approvals for financing, delivering corporate outcomes and delivery timetable;

• Financial appraisals for funding and ongoing revenue costs

• Spend profiles against delivery timetable;

• End of project reviews;

• Delivery of Asset Management Plans and overall strategy.

3.3The City Council will continue to identify future funding streams that are available to both itself and private developers to promote ongoing regeneration and investment.

4. Original and latest proposed capital programme for 2013/14

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 2 pages Download
PDF
Appendix 4Appendix 4 2 pages Download
PDF
Appendix 5Appendix 5 1 pages Download
PDF
Capital Programme Monitor 2013/14: Month 9 (December 2013)Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Capital Programme Monitor 2013/14 - Month 9 (December 2013)This decision
  2. Corporate Risk Register Deep Dive - CR2 Capital ProgrammesAgreed
  3. Capital Programme 2019/20 - Final Outturn PositionDecided
  4. Capital Programme Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Capital Programme Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Capital Programme Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies