Resolved
Resolved that the recommendation be approved. R/35
Cabinet 2010/21 approved this item on Friday 21 February 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved. R/35
As part of the proposed budget saving options for 2014/2015, the City Council has been looking at those areas where there is the potential to significantly reduce costs.
The Council currently spends approximately £2.6m per annum on energy costs associated with street lighting. In addition to this, approximately 69% of the Council's total lighting stock are SOX type lanterns which are costly both in terms of energy consumption and ongoing maintenance costs, primarily due to the age of the asset. The proposal outlined within this report, and for which approval is sought, involves the replacement of the existing SOX lanterns with LED lanterns on steel lighting columns.
Based on an investment of £7m over a two-year period, there will be two initial phases to the lantern replacement project with £3m investment per phase:
(i) the first phase of the project, which it is proposed be implemented during 2014/2015, will involve the replacement of approximately 12,000 of the existing SOX lanterns with LED. The residential areas along the waterfront will be targeted initially as the lighting in this area is that which is subject to the greatest environmental impact in terms of wind, salt etc. As a result, the SOX lamps along the waterfront area also have the highest failure level and hence result in the highest replacement costs. (ii) the second phase of the project, which it is proposed be implemented during 2015/2016, will involve the replacement of approximately 8,000 of the existing SOX lanterns with LED within residential areas, and the replacement of approximately 1,380 of the existing SOX lanterns with LED along a number of key corridors into the city.
(iii) an additional £1m has been built into the programme to allow for the replacement of up to 800 columns if this is considered necessary for health and safety reasons.
The £7m investment proposal will result in the following benefits:
General
• Significantly improved lighting levels in those areas targeted, resulting in an improved perception of safety. • Significant reduction in the maintenance costs associated with those columns treated, with a 15-year warranty for both the LED units and the photocells. • An immediate saving in the Core Service cost for lighting, linked to the mechanisms contained within the Highway Services contract with Amey LG Limited. • A reduction in the number of street lighting columns at potential risk of failure.
Phase 1 (Proposed Implementation – 2014/2015)
• A reduction of 82% in the energy consumption for those columns treated, equating to approximately £273k per year, rising by inflation. • A three year 'energy cash back' initiative with the lantern supplier for the remaining 18% energy, equating to approximately £60k per year for a three-year period. • A reduction in Carbon of approximately 1,400 tonnes, which equates to a saving of approximately £23k, rising by at least inflation per annum. This investment will mitigate future carbon tax rises. • Significant reduction in the maintenance costs associated with those columns treated, with a 15-year warranty for both the LED units and the photocells. • Ongoing maintenance savings of approximately £60k per annum associated with the Highway Services contract.
Phase 2 (Proposed Implementation – 2015/2016)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Street Lighting: LED Implementation Programme (TCC/11)Report | 21 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.