Resolved

Resolved that – (i) the Chief Executive be authorised to accept the DCMS grant agreement to access funding from the £40m national pot from 1 st April 2015 until 31 st March 2016. This funding is to support a voucher scheme to SMEs in the Liverpool City Region of up to a maximum of £3,000 towards the capital costs of a broadband connection; (ii) the City Council accepts the role of accountable body for the scheme across Liverpool City Region; (iii) the Corporate Capital Programme be amended to reflect the profile of expenditure and funding sources detailed in the financial implications section of the report submitted; (iv) the Assistant Chief Executive be authorised to implement the voucher scheme in line with BDUK requirements and procedures; (v) the Assistant Chief Executive be appointed as the Nominated Officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (vi) authority be granted to commit to expenditure as requested within the approval; (vii) further reports be submitted in the event of any significant variance to this scheme; and (viii) it be noted that there is no match funding requirement from the City Council and that project management costs can be covered from a top slice of funding from the grant allocation. This will be monitored and managed by the Assistant Chief Executive. N/6
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 7 pages

Executive summary

Cabinet granted authority in July 2014 for the City Council to participate in the Government’s Superfast Broadband Connection Voucher scheme for SMEs. This scheme offers a voucher for SMEs in Liverpool of up to £3,000 towards the capital costs of a super/ultra-fast broadband connection.

The Superfast Broadband Connection Vouchers scheme is a national government initiative, managed by Broadband Delivery UK (BDUK), a team within DCMS. It is aimed at improving broadband connectivity in the major cities of the UK.

Liverpool City Council has been operating the connection vouchers scheme in Liverpool since August 2014. There has been good take up of the scheme to date and the vouchers have proved very popular with a wide range of SMEs. Liverpool was offered an allocation of £1.5m which can support approximately 500 vouchers and the City Council has been managing the scheme and making the appropriate grant payments in line with the conditions of the scheme.

BDUK have now granted Liverpool City Council permission to expand the scheme to cover the wider Liverpool City Region area (ie. to include Halton, Knowsley, Sefton, St Helens and Wirral) from the 1st April 2015. Government have allocated an additional £40m funding pot nationally which will be drawn upon by participating cities on a first come first served basis, with the scheme coming to a close at the end of March 2016.

The background and more detail on the workings of the scheme can be found in the Cabinet report dated 4th July 2014.

Background

This report seeks cabinet approval for the City Council to continue to operate the scheme on the same basis but over the wider Liverpool City Region area subject to the operational arrangements outlined below.

Operation of the Liverpool City Region wide Broadband Connection Vouchers scheme.

This report proposes that Liverpool City Council continues to operate the scheme but over the wider Liverpool City Region area (It should be noted that BDUK are restricting the administration of the scheme to cities only and so individual local authorities in the City Region would not be permitted to run their own scheme in their areas).

To this end, Liverpool City Council would process the voucher applications and payments, liaise with suppliers and undertake a small amount of central marketing activity for the scheme, with individual Local Authorities undertaking localised marketing and demand stimulation activity in their areas.

However at certain times, the number of applications may become unmanageable for a short period, for example at the start of the scheme when demand is at its highest. If this occurs, in order for the City Council to manage the workload, we are proposing that an appropriate officer from the Districts (in rotation) should spend for example half a day processing some vouchers for their area to clear any backlog. It is not anticipated that the requirements for support will be any more than half a day every 6 weeks. The City Council will continue to do the central reporting and claims.

The scheme is very straightforward to operate and process and this suggestion has been agreed with City Region Authorities. .

Liverpool City Council is able to claim 10% of the value of vouchers that are taken up to cover costs relating to administering the scheme and possibly any central demand stimulation activities if resources allow. Mayoral Recommendation: That –

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Superfast Broadband Connection Vouchers Scheme for SMEs: Expansion to cover LCR (M/20)Report 7 pages DownloadRead as text

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies