Cabinet 2010/21, Thursday 2 April 2015

Revenue Monitor 2014/15 - Month 11 (February 2015)

Approved Executive 5 papers

Cabinet 2010/21 approved this item on Thursday 2 April 2015. Below is the council's own wording, with the papers it was decided on.

Item402b

Resolved

Resolved that Cabinet – (i) note that on the 5 th March 2014 the City Council set a 3 year balanced budget for the years 2014/15 to 2016/17 taking budget savings decisions to close a £156.8m budget gap. This is on top of successfully bridging a budget gap of £173.4m from 2011/12 to 2013/14. This gives context to the current financial forecast for 2014/15; (ii) note at the end of Month 11 (February 2015) the full year forecast projects a general fund underspend of £1.494m after the drawdown of earmarked reserves. This is made up of a forecast year end overspend of £1.935m across the Directorates fully mitigated by a forecast year end underspend of £3.429m on capital financing costs. The forecast year end underspend will be taken to reserves to mitigate against the impact of budget savings decisions for 2015/16 and 2016/17. The Dedicated Schools Grant (DSG) funded activities are forecast to break even after the use of earmarked reserves; (iii) approve the £1.239m of earmarked reserve requests detailed in section 6 of the report submitted; and (iv) note that there are a number of risks and uncertainties that may impact adversely on the general fund financial forecasts for the remainder of 2014/15. These are shown in Section 5 of the report and include increased demand pressures for services, impact of the economic downturn, claims made against the City Council and that of the 2014/15 Directorate budget savings decisions £63.291m (94%) have been delivered. Of the remaining decisions still to be delivered £0.324m have been identified as green, £2.184m identified as amber, £0.500m identified as red and these have been factored into the forecasts.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 12 pages

Revenue Monitor 2014/15 Month 11 (February 2015) LIVERPOOL CITY COUNCIL

Cabinet – 2nd April 2015

Joe Anderson OBE Mayor of Liverpool

Contact Officers:

Becky Hellard – Director of Finance & Resources – 0151 225 2347 [email protected]

Peter Casterton - Head of Finance - 0151 225 2596 [email protected] SUBJECT: REVENUE MONITOR 2014/15 MONTH 11 (February 2015)

Summary The report sets out the revenue forecast for 2014/15 as at Month 11 and future reports will identify ongoing management actions to ensure that the year-end position will result in a managed year end budget underspend.

Recommendations Cabinet is requested to: (i) Note that on the 5th March 2014 the City Council set a 3 year balanced budget for the years 2014/15 to 2016/17 taking budget savings decisions to close a £156.8m budget gap. This is on top of successfully bridging a budget gap of £173.4m from 2011/12 to 2013/14. This gives context to the current financial forecast for 2014/15.

(ii) Note at the end of Month 11 (February 2015) the full year forecast projects a general fund underspend of £1.494m after the drawdown of earmarked reserves. This is made up of a forecast year end overspend of £1.935m across the Directorates fully mitigated by a forecast year end underspend of £3.429m on capital financing costs. The forecast year end underspend will be taken to reserves to mitigate against the impact of budget savings decisions for 2015/16 and 2016/17. The Dedicated Schools Grant (DSG) funded activities are forecast to break even after the use of earmarked reserves.

(iii) Approve the £1.239m of earmarked reserve requests detailed in section 6 of this report.

(iv) Note that there are a number of risks and uncertainties that may impact adversely on the general fund financial forecasts for the remainder of 2014/15. These are shown in Section 5 of the report and include increased demand pressures for services, impact of the economic downturn, claims made against the City Council and that of the 2014/15 Directorate budget savings decisions £63.291m (94%) have been delivered. Of the remaining decisions still to be delivered £0.324m have been identified as green, £2.184m identified as amber, £0.500m identified as red and these have been factored into the forecasts. REPORT 1. Background

1.1Revenue budget monitors are produced each month of the financial year with a year end report in June, as set out in the schedule at Appendix 1. The reports track progress against the agreed budget decisions, forecast any anticipated significant variances to the budget, and enables corrective action to be taken.

2. Overall Position

2.1The projected revenue forecast for the year, at Month 11 (February 2015), shows a forecast year end underspend of £1.494m on the General Fund after the drawdown of earmarked reserves. The year end underspend will be taken to reserves to mitigate against the impact of budget savings decisions for 2015/16 and 2016/17. There are various budget pressure identified across the Directorates and these are detailed in Section 3 of this report. Note that the forecast year end position for 2014/15 is after closing a budget gap of £173.4m over the last 3 years.

2.2Management actions will be identified to alleviate the budget pressures identified in this report to ensure that there is no adverse impact on Working Balances. There are 2 months of the financial year left to mitigate the budget pressures identified.

2.3Changes to the budget have occurred since it was approved by City Council in March 2014 and these are summarised in Table 1 and mainly related to movement on reserves and capital financing charges. These changes are detailed in Appendix 2.

Table 1: 2014/15 Original & Revised Net Budget analysed by Directorate (£000s) Original Approved Approved Revised Budget Budget Budget Net Book Virements Virements Budget Month 1-10 Month 11 £000s £000s £000s £000s

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 3 pages Download
PDF
Revenue Monitor 2014/15: Month 11 (February 2015)Report 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Revenue Monitor 2014/15 - Month 11 (February 2015)This decision
  2. Revenue and Capital Finance Monitor Report 2025-26 Outturn & Medium Term Financial Strategy – Approach for 2027-28 onwardsNoted
  3. Revenue and Capital Financial Monitoring Report 2025/26 (Quarter 4)Noted
  4. Revenue Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Revenue Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Revenue Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies