Resolved
Resolved that the recommendation be approved. EDCS/16
Cabinet 2010/21 approved this item on Friday 17 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved. EDCS/16
Following the completion of feasibility studies and pre-construction activity over the past 4-months, this report seeks authority to award the construction contracts for Crown, Granby and Sedgemoor Adult Reablement and Community hubs as the Phase 2 investment in the City’s hubs.
Background Information
Following investment in hubs under Phase 1 (which consisted of a comprehensive refurbishment of Lime, a new build element to Sedgemoor and refurbishment of the communal areas within Sedgemoor and Granby). Feasibility and design commenced in late-2014 on the Phase 2 projects. This will see further refurbishment at Granby and Sedgemoor Reablement Hubs to primarily bedrooms, bathrooms/en-suites bathrooms and corridors and, a comprehensive refurbishment and new build extension to Crown Street Day Resource Centre.
Proposals for the Hubs
Crown A proposed new build extension to create a new entrance visitor area and cafe. The existing building will be completely remodelled to create accommodation for leaning bases and rooms. External works will also see improvements to car park and landscaping.
Granby Proposed themed refurbishment to all 30 bedrooms including walls, joinery, flooring, lighting and furniture and new en-suite bathroom fit-outs. Refurbishment will also extend to communal bathrooms, dining area’s and lounges together with the upgrade of external areas and the central courtyard.
Sedgemoor Proposed themed refurbishment to all 30 bedrooms including walls, joinery, flooring, lighting and furniture and new en-suite bathroom fit-outs. Refurbishment will also extend to the corridors and communal bathrooms, lounge, dining areas.
Following consultation with centre managers and service users, sample rooms will be completed in advance of awarding the contracts to agree the specification before committing to the full refurbishment.
Procurement and Management
The management of the project will be undertaken by Regeneration working with Adult Social Care and Health as Client. The procurement route undertaken for the works is similar to a number of schools delivered under the Liverpool’s School Investment Programme through the Scape National Framework with Willmott Dixon Construction (WDC). Scape and WDC are both heavily committed to maximising local spend through the supply chain which has been demonstrated to date through the school projects. The Lime hub external works scheme was recently completed through Scape.
Pre-construction activity (design, site investigations and planning) has been undertaken through Project Orders issued to WDC. Subject to agreeing a final Lump Sum price with WDC, this report seeks authority to award an advanced works orders to undertake preliminary site works and authority to award the full construction contracts to achieve the required completion dates.
Planning Permission
Planning consent is only required for the works at Crown Street and a decision is expected in mid-March 2015.
Phasing and Timescales
The following timescales are proposed for the construction works:
Sample room – late March 2015 Crown: late-April to late October 2015 (26 weeks)
Granby: late-April to mid-August 2015 (16 weeks)
Sedgemoor: late-August to late-December 2015 (18 weeks)
Hub Closures
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Adult Reablement and Community Hubs: Phase 2 (ASC/9)Report | 10 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.