Cabinet 2010/21, Friday 17 April 2015

Adult Reablement and Community Hubs – Phase 2 (ASC/9)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 17 April 2015. Below is the council's own wording, with the papers it was decided on.

Item408a

Resolved

Resolved that the recommendation be approved. EDCS/16
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 10 pages

Executive summary

Following the completion of feasibility studies and pre-construction activity over the past 4-months, this report seeks authority to award the construction contracts for Crown, Granby and Sedgemoor Adult Reablement and Community hubs as the Phase 2 investment in the City’s hubs.

Background Information

Following investment in hubs under Phase 1 (which consisted of a comprehensive refurbishment of Lime, a new build element to Sedgemoor and refurbishment of the communal areas within Sedgemoor and Granby). Feasibility and design commenced in late-2014 on the Phase 2 projects. This will see further refurbishment at Granby and Sedgemoor Reablement Hubs to primarily bedrooms, bathrooms/en-suites bathrooms and corridors and, a comprehensive refurbishment and new build extension to Crown Street Day Resource Centre.

Proposals for the Hubs

Crown A proposed new build extension to create a new entrance visitor area and cafe. The existing building will be completely remodelled to create accommodation for leaning bases and rooms. External works will also see improvements to car park and landscaping.

Granby Proposed themed refurbishment to all 30 bedrooms including walls, joinery, flooring, lighting and furniture and new en-suite bathroom fit-outs. Refurbishment will also extend to communal bathrooms, dining area’s and lounges together with the upgrade of external areas and the central courtyard.

Sedgemoor Proposed themed refurbishment to all 30 bedrooms including walls, joinery, flooring, lighting and furniture and new en-suite bathroom fit-outs. Refurbishment will also extend to the corridors and communal bathrooms, lounge, dining areas.

Following consultation with centre managers and service users, sample rooms will be completed in advance of awarding the contracts to agree the specification before committing to the full refurbishment.

Procurement and Management

The management of the project will be undertaken by Regeneration working with Adult Social Care and Health as Client. The procurement route undertaken for the works is similar to a number of schools delivered under the Liverpool’s School Investment Programme through the Scape National Framework with Willmott Dixon Construction (WDC). Scape and WDC are both heavily committed to maximising local spend through the supply chain which has been demonstrated to date through the school projects. The Lime hub external works scheme was recently completed through Scape.

Pre-construction activity (design, site investigations and planning) has been undertaken through Project Orders issued to WDC. Subject to agreeing a final Lump Sum price with WDC, this report seeks authority to award an advanced works orders to undertake preliminary site works and authority to award the full construction contracts to achieve the required completion dates.

Planning Permission

Planning consent is only required for the works at Crown Street and a decision is expected in mid-March 2015.

Phasing and Timescales

The following timescales are proposed for the construction works:

Sample room – late March 2015 Crown: late-April to late October 2015 (26 weeks)

Granby: late-April to mid-August 2015 (16 weeks)

Sedgemoor: late-August to late-December 2015 (18 weeks)

Hub Closures

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Adult Reablement and Community Hubs: Phase 2 (ASC/9)Report 10 pages DownloadRead as text

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies