The purpose of this report is to authorise capital expenditure of £411,954 relative to an Exchequer Funding Award (EFA) from Sport England to supply and install a modular changing facility at Clubmoor Recreation Ground.
Liverpool City Council was invited to make an application to the targeted 2014-15 Exchequer programme on New Technologies in Sports Lighting and Modular Design. This programme supports projects which will pilot new approaches to facility design. Liverpool City Council’s application was submitted under Unique Reference Number 2014017879 and requested financial support in 2014-15 in relation to the provision of the Project.
The preferred site is Clubmoor Recreation Ground which has insufficient changing accommodation to serve all existing adult grass pitches. Teams currently use the modest changing facilities located within the adjacent housing association building operated by Liverpool Mutual Homes (LMH) for which Sport and Recreation pay an annual fee of circa £6k. When the new changing facility is completed, this budget will be used to cover the ongoing revenue costs associated with its operation. The design of the modular building will allow future extensions (funded by the Football Foundation) thus removing the need to retain use of the adjacent LMH facilities.
This proposal has been communicated to the Cabinet Member and local ward councillors who are supportive of the opportunity and planning approval has been obtained.
The Project will see the (off-site) construction of a four team changing facility at Clubmoor Recreation Ground, Townsend Lane, Liverpool, L13 9DY. The new facility will support football activity on the site which is a 6 grass pitch central venue for U18 and U21 Leagues with no current changing provision on site.
The Exchequer Funding Agreement (Deed) sets out the terms and conditions upon which Sport England agrees to make the Exchequer Grant available to Liverpool City Council.
Mayoral Recommendation: That –
(i) Authority be given to commit Sport England Funded expenditure of £411,954 to construct a new four team changing room at Clubmoor Recreation Ground; (ii) to amend the 2015/16 and 2016/17 City Council Capital Programme accordingly; and (iii) further reports be submitted in the event of any significant variance to this profile.
Mayor’s Priorities The recommended action will support the Mayor’s pledge to Make the City Greener, Cleaner and Healthier by enabling residents to find a physical activity that they can enjoy throughout their lifetime, resulting in them becoming healthier, both physically and mentally, reducing the long term reliance on health services.
Corporate Aim(s):
We will empower people to enjoy the best possible quality of life and reach their full potential;
Enhancing provision and services for people aged 14+ will improve their quality of life and reduce health inequalities therefore increasing the vitality of residents. This will further residents’ sense of place. The project is part of a national initiative being delivered through Sport England funding and our contribution to increasing physical activity levels will enhance our national profile.
We will build strong, attractive and accessible neighbourhoods:
Participation in the project will encourage people aged 14+ to become more involved with their wider community. Local people will be encouraged to work together in order to shape the delivery of the programme. This could benefit other areas of service provision for people aged 14+.
Key Decision: No
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sport England: Exchequer Funding Award (CTE/10)Report | 5 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.