Cabinet 2010/21, Friday 3 March 2017

Knowledge Quarter Gateway Masterplan and approval of "In Principle" CPO Powers (RTC/38)

Approved Executive 2 papers

Cabinet 2010/21 approved this item on Friday 3 March 2017. Below is the council's own wording, with the papers it was decided on.

Item97b

Resolved

This report seeks approval for the City Council to produce a Masterplan for the area bounded by Mount Pleasant, Brownlow Hill and the western terrace of Lime Street to include the former 051 Club and the wider area in which the Adelphi Hotel is located. The report also sets key aims and objectives for development and regeneration on a phased approach. This area is collectively known as the Knowledge Quarter Gateway and presents the opportunity for significant investment, redevelopment and job creation at this key location. The report also seeks “in principle” approval for the Council to use its compulsory purchase powers (under Section 226(1) (a) of the Town and Country Planning Act 1990) to facilitate the acquisition and development of land and property (as shown edged red on Plan 1, Appendix 1) in the same area.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 16 pages

Executive summary

This report seeks approval for the City Council to produce a Masterplan for the Knowledge Quarter Gateway area bounded by Mount Pleasant, Brownlow Hill and the western terrace of Lime Street to include the former 051 Club and the wider area in which the Adelphi Hotel is located. The report also sets key aims and objectives for development and regeneration on a phased approach.

The Knowledge Quarter Gateway area presents an opportunity for significant investment, redevelopment and job creation at this key location.

The report also seeks “in principle” approval for the Council to use its compulsory purchase powers (under Section 226(1) (a) of the Town and Country Planning Act 1990) to facilitate the acquisition and development of land and property (as shown edged red on Plan 1, Appendix 1) in the same area.

Background

Now that the development of the eastern terrace of Lime Street has commenced, there is a clear opportunity for new development for the Knowledge Quarter Gateway area to be a catalyst for further regeneration and provide a positive impact on the rest of Lime Street, Mount Pleasant and Copperas Hill, and to establish the area as a key gateway between the City Centre and the Knowledge Quarter. The vision and aspirations for the area have been previously identified in the City Centre Strategic Investment Framework.

Strategic Investment Framework (SIF) - 2012

The Liverpool City Centre Strategic Investment Framework (SIF) 2012 is the strategy which guides investment across the City Centre over a 15-year period. It establishes protocols for the continued growth of the City Centre during this period and beyond, as its economic position develops.

Within the Liverpool City Centre SIF, the site area at Mount Pleasant and Brownlow Hill is referenced as the ‘Knowledge Quarter Gateway’ and is highlighted as a key transformational project within the Knowledge Quarter area of the City.

The Council and its strategic ‘Knowledge Quarter’ partners including the Universities, Liverpool Science Park, The School of Tropical Medicine and the Royal Liverpool and Broadgreen University Hospital Trust (RLBUHT) are working collaboratively to encourage and drive regeneration within the City’s Knowledge Quarter to support new education, residential, innovation and business opportunities.

The Knowledge Quarter economy sector of the City is identified as a highly productive area, with Liverpool already the home of key specialisms. The area contains some of the City’s key academic and research assets, including the University of Liverpool, Liverpool John Moores University, Hope University, the Royal Liverpool University Teaching Hospital and the Liverpool School of Tropical Medicine. The Life Sciences University Technical College is also being established in the City Centre. Major opportunities exist and are being taken forward to develop the Bio Sciences sector focused around the Knowledge Quarter, with the Universities and other research and development institutions at the heart of the strategy, which focuses spatially on a vibrant and growing Knowledge Quarter.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Knowledge Quarter Gateway Masterplan and approval of "In Principle" CPO Powers (RTC/38)Report 16 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Knowledge Quarter Gateway Masterplan and approval of "In Principle" CPO Powers (RTC/38)This decision
  2. Upper Central (Formerly Knowledge Quarter Gateway) Spatial Regeneration Framework – Public Consultation Feedback and Endorsement of Final SRF (M/46)Decided
  3. Knowledge Quarter Development Company (Sciontec Liverpool) (M/55)Decided
  4. Knowledge Quarter Gateway - Further update (M/37)Agreed
  5. Knowledge Quarter Public Realm Phase 3 - Mount Pleasant and Links (A&D/24)Approved
  6. Knowledge Quarter Public Realm Package 2: Brownlow Hill and Wilderness Area (A&D/58)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies