Primary School Expansion Programme – Award of Construction Contract, Sudley Infant School (RTC/53)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 19 May 2017. Below is the council's own wording, with the papers it was decided on.

Item122g

Resolved

This report seeks authority to award the construction contract for works at Sudley Infant School in relation to the approved expansion of the school from 3 to 4 forms of entry
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 8 pages

Executive summary

This report seeks authority to award the construction contract for works at Sudley Infant School in relation to the approved expansion of the school from 3 to 4 forms of entry

Background Information

On 16th December 2016 the Cabinet approved a recommendation that –

The City Council publishes statutory proposals to make prescribed alterations:

(a) to enlarge the premises of Sudley Community Infant School to enable the capacity of the school to increase from 270 to 360 phased over three academic years commencing in September 2017

Statutory Notices in respect of the proposals were published on 9 January 2017. Following the expiry of the statutory consultation period and in the absence of objections the expansion of Sudley Infant School was approved by the Director of Children’s and Young Peoples Services under powers delegated by Cabinet.

This report seeks approval to the award of the construction contract to undertake the works required to accommodate the additional pupils.

Project Proposals

The project comprises:

 an extension at the rear to provide an additional reception class, learning resource base and ancillary accommodation including extra wc’s and storage;

 an extension onto the front admin block to create a new staffroom;

 internal remodelling of the current staffroom and learning resource to create new year 1 and year 2 classrooms;

 associated external works including landscaping and remodelling of the car park.

Procurement

Pre-construction orders have been placed with Kier Construction under the Scape Minor Works Framework to develop the project up to the point of contract award. This report seeks authority to award the construction contract for the works through to completion.

Timescales

Contract award for the above is planned for June 2017 for completion of all works by February 2018.

Planning Permission and other consents

A full planning application (Ref: 17F/0594) has been submitted and is awaiting determination.

Local Spend and Employment

Kier have indicated the following targets for all projects; Liverpool 65% and Merseyside 85%. Market testing by Kier is ongoing and the selection of sub- contractor works packages will continue beyond the main contract award. As such, Kier will assess each work package as it approaches sub-contract award stage to maximise local spend.

The opportunities for local apprentices already achieved during the Liverpool Schools Investment Programme will be maximised and will be agreed with ‘Liverpool in Work’ and ‘Employment Initiatives’ with the Council. Due to the value and limited time the projects are on site apprenticeships will mainly be taken from existing apprenticeship placements. However, the City Council is working with Kier Construction Ltd to develop further opportunities during the delivery phase in this regard. All labour working on the sites that pass through the site gates will be monitored by postcode and local labour will be monitored through the life of the project.

Mayoral Recommendation: That –

(i) in respect of works to Sudley Infant School, the City Council sign a Memorandum of Agreement (construction contract) with Kier Construction (Liverpool) under the Scape Minor Works Framework up to a maximum contract value of £1,200,000 (including expenditure committed and spent through pre-construction stage Project Orders). In lieu of a bond, a Parent Company Guarantee is to be provided by the contractor;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Primary School Expansion Programme: Award of Construction Contract, Sudley Infant School (RTC/53)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Primary School Expansion Programme – Award of Construction Contract, Sudley Infant School (RTC/53)This decision
  2. Wavertree Primary School – Extension Refurbishment (E/14)Decided
  3. Permission to post Statutory Notices – Proposal to expand Blueberry Park Primary School (E/15)Decided
  4. Proposal to Expand Blueberry Park Primary SchoolAgreed
  5. Publication of Statutory Proposals - Changes to Language Resourced Provision at Four Oaks Primary School (E/15)Decided
  6. Community Primary & Secondary Schools Admission & Co-ordinated Admission arrangements 2020/21(E/7)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies