Liverpool City Council
Cabinet 2010/21, Friday 9 February 2018

Cruise Terminal Liverpool Spigot Repair (M/18)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 9 February 2018. Below is the council's own wording, with the papers it was decided on.

Item79g

Resolved

The purpose of this report is to seek authority carry out urgent replacement work to the remaining two of the original spigot hinges that were damaged by Strom Eleanor in January 2018. This report also provides an update on the progress made since the Cabinet approval obtained in September 2016 to undertake the detail design and repair and or replace the Spigot hinges that connects the four floating pontoons, which forms the landing stage/berth for cruise ships.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 6 pages

Executive summary

The purpose of this report is to seek authority carry out urgent replacement work to the remaining two of the original spigot hinges that were damaged by Strom Eleanor in January 2018.

This report also provides an update on the progress made since the Cabinet approval obtained in September 2016 to undertake the detail design and repair and or replace the Spigot hinges that connects the four floating pontoons, which forms the landing stage/berth for cruise ships

Currently out of the six spigot hinges, four spigot hinges have been successfully replaced with a new design that is considered robust to withstand the tidal conditions of the River Mersey and also easy to maintain. These Spigot hinges bind the pontoons together and provide greater stability when the berth is subjected to sea swell and tidal movement.

Approval is now sought for the full replacement of the last two spigot hinges between Pontoons C and D (damaged by Storm Eleanor) to be replaced with similar type to the four spigots that were installed between Pontoons A,B & C. Information:

Background / Progress Update

Liverpool Cruise Liner Berth is constructed using four interconnected floating pontoons. The pontoons are constructed in reinforced concrete and are secured to each other primarily by two steel spigot pieces located within sockets in the adjacent pontoons. The pontoons are also individually secured to steel piles driven into the riverbed to hold them in position. The two hinges allow freedom of movement in the longitudinal and transverse directions, but constrain the two adjacent pontoons in the vertical direction. Therefore when there is sea swell, waves, tidal surge and movement the hinges provide a dampening mechanism that reduces vertical and lateral movement enabling a more stable platform to carry out operations. The buoyancy of the pontoons is not affected.

Following the Cabinet approval obtained on the 30th September 2016(Report RTC/21) to carry out major refurbishment of the spigot hinges, and following a competitive procurement exercise John Sisk & Son was appointed to fully replace four of the completely damaged spigots between Pontoons A, B and C. These works were successfully completed in July 2017. Subsequently in August 2017, John Sisk and Son were instructed to repair the other two Spigots between Pontoons C and D (rather than full replacement) as they were thought to be in a reasonable condition.

Furthermore, as at the time the City Council were also considering the design of the new Cruise Liner Terminal and a design option to replace Pontoons C and D with wider pontoons, and it was thought prudent to carry out an interim repair solution to the spigots between Pontoons C and D would be more appropriate and a cost effective solution. Once the new Cruise Terminal design was more confirmed then the cost of replacement could potentially fall under the remit of the capital project.

In January 2018, while carrying out the interim repair to the spigots between Pontoons C and D, Storm Eleanor damaged the holding bolts of the spigots and the bolt housing in the Pontoon D in a manner that without a total rebuild of the Pontoon wall and fixing new bolt housing the repair may not be possible. Therefore, the ongoing works to the “interim” repair solution to the spigots in Pontoon D have been suspended until the damaged is fully assessed and options for the repair are investigated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cruise Terminal Liverpool Spigot Repair (M/18)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Cruise Terminal Liverpool Spigot Repair (M/18)This decision
  2. Update on the New Cruise Liner Terminal Project (M/56)Decided
  3. Re-Tender for Stevedore & Rope-handling services at Liverpool Cruise Terminal (CTE/2)Approved
  4. New Cruise Terminal & Supplementary Projects - Progress Update (M/5)Approved
  5. Cruise Terminal Liverpool (M/17)Decided
  6. Cruise Terminal Liverpool - Update (RTC/50)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies