The City Council (LCC), Your Housing Group (YHG), Liverpool Football Club (LFC) and Keepmoat Homes are continuing to work collaboratively to deliver comprehensive regeneration and long-term benefits for the Anfield area. The Anfield Project involves comprehensive regeneration of the area with project investment estimated to be in the region of £225m, which could lead to the creation of 770 jobs. The Project has already delivered 600 new and 600 refurbished homes, an expansion of the LFC stadium and revitalised Stanley Park. A planning application is to be submitted by Keepmoat for the final Phase of the Anfield/Brickfield housing renewal comprising 86 dwellings, and YHG also has housing proposals. This would total a further 150 new and refurbished homes. The first of three phases of new retail development on Walton Breck Road is at the planning application stage. Plans are advancing for a high-end brand hotel with training element at Anfield Square. The first phase of environmental works have been delivered in Anfield Village, and subject to Cabinet approval these works will be completed later this year. This will be followed by a comprehensive public realm improvement scheme for Walton Breck Road.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Cabinet Member: Joe Anderson OBE, Mayor of Liverpool
Director: Nick Kavanagh, Director of Regeneration & Employment
Purpose of Report: Anfield Project - Land acquisitions/disposals, demolitions and land assembly to facilitate environmental works & housing development
Date: Report No: 20th April 2018 EDR/31/18
Decision Type: Cabinet Key Decision
Executive Summary: The City Council (LCC), Your Housing Group (YHG), Liverpool Football Club (LFC) and Keepmoat Homes are continuing to work collaboratively to deliver comprehensive regeneration and long-term benefits for the Anfield area.
The Anfield Project involves comprehensive regeneration of the area with project investment estimated to be in the region of £225m, which could lead to the creation of 770 jobs. The Project has already delivered 600 new and 600 refurbished homes, an expansion of the LFC stadium and revitalised Stanley Park.
A planning application is to be submitted by Keepmoat for the final Phase of the Anfield/Brickfield housing renewal comprising 86 dwellings, and YHG also has housing proposals. This would total a further 150 new and refurbished homes. The first of three phases of new retail development on Walton Breck Road is at the planning application stage. Plans are advancing for a high-end brand hotel with training element at Anfield Square. The first phase of environmental works have been delivered in Anfield Village, and subject to Cabinet approval these works will be completed later this year. This will be followed by a comprehensive public realm improvement scheme for Walton Breck Road. The purpose of this report is to seek authority to :
1. Reaffirm previous Cabinet approvals to carry out demolitions in Anfield Village for the purpose of land assembly so as to carry out street works / environmental improvements identified in the Anfield SRF.
2. Acquire 17 YHG assets with the intention of demolishing tem for land assembly and completing Phase 2 of the street works / environmental improvements in Anfield Village.
3. Agree the design for Phase 2 of the street works / environmental improvements in Anfield Village, including a new housing development component as an alternative to public open space originally envisaged.
4. Dispose of the Council’s freehold interests in land and property at best consideration in Anfield Village to YHG to facilitate delivery of residential development.
5. Allow YHG exclusivity to work up a business case and design for a residential development scheme on Phase 2A of the Anfield/Breckfield housing renewal area.
6. Acknowledge that the Partners continue to progress with an alternative development partnership to deliver a high-end hotel with training element at Anfield Square.
Approval by Cabinet to the land and property transactions, and YHG’s residential development proposals, will facilitate regeneration of derelict sites within the Anfield, and thereby allow the Anfield Regeneration Project to continue. This demolition of derelict properties and the environmental enhancement of cleared land will remove visual blight and the poor perception of the area, enabling the creation a revitalised neighbourhood in Anfield Village. It also presents the opportunity for a range of new and refurbishment homes, contributing towards the overarching objective of housing renewal and sustainable communities in Anfield. In doing so this will enable YHG to reinvest receipts from land and property transfers into the wider Anfield area. It also allows the delivery of a high-end hotel with training element at Anfield Square to proceed.
Information:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
103lAnfield Project - Land acquisitions/disposals, demolitions and land assembly to facilitate environmental works & housing development (M/47)This decision
Anfield Project - Land acquisitions/disposals, demolitions and land assembly to facilitate environmental works & housing development (M/47)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.