Resolved
Expansion of Belvedere Academy
Cabinet 2010/21 decided this item on Friday 8 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Expansion of Belvedere Academy
CABINET
PRINCES PARK WARD PUBLIC E/11
Cabinet Member: Councillor Barbara Murray Cabinet Member, Education
Director: Nick Kavanagh, Director – Regeneration & Employment Services
Purpose of Report: Expansion of Belvedere Academy
Date: Report No: 8 February 2019 EDR/85/18
Decision Type: Cabinet Key Decision
Executive Summary: In order to meet the demand for secondary school places there is a need to expand provision in a number of schools across the City. At the Belvedere Academy the proposal is to expand by 1 form of entry or 25 places per year group from September 2019, increasing its current admission number from 130 to 155 places. The expansion requires the construction of a new two storey teaching block, internal alterations to form 2 science labs and appropriate external works.
Information: Councils have statutory duties to ensure there are sufficient schools places. The Department for Education make basic need allocations to local authorities (LAs) to support the capital requirement for providing new pupil places by expanding existing maintained schools, free schools or academies, and by establishing new schools.
Pupil numbers in Year 7 to Year 11 are expected to be almost 19% higher in 2023/2024 compared to 2015/16 – 23,110 compared to 28,666 (an increase of 5,556 pupils). Projections are based on Census data, using Y6/7 retention rates and percentages from out of city are applied to the feeder rates for schools. This is then applied to the pupil numbers on roll (NOR) for Reception to Y6 to give projected numbers. The effect of planned housing is calculated in.
In 2019 the projections are showing a large shortfall of in excess of 250 places.
In addition the LA will require some surplus in the system to allow for late applications and families moving into the city.
Whilst developing the Secondary Pupil Place Planning Strategy, visits and discussions have been held with most secondary sector schools in regard to future Year 7 intakes and the need for additional places.
It was identified during these visits that approximately half the required places could be provided within current accommodation, with small increases across a number of schools. The rest would require investment.
Within the secondary sector there is an average 6.5% net gain of pupils entering Year 7 for Liverpool schools from neighbouring authorities. This may be concentrated in specific areas due to admissions policies.
The Belvedere is one of the schools that has random allocation as an admissions criteria therefore pupils can gain entry from any location outside Liverpool.
Another key factor in planning is the gender breakdown of Liverpool secondary schools. It has one of the highest numbers of single sex schools of any local authority.
The LA needs to ensure, when adding additional places in single sex schools, that they create a balance of provision.
In order to meet the initial deadline of September 2019 for providing the places so far identified the Council is working with those schools that have expressed a firm interest to expand.
The expansion of the Belvedere will be phased providing an additional 25 places for September 2019 (increasing the published admission number from 130 to 155) expanding to full capacity with an additional 125 places through years 7 to 11 by 2023.
The proposed works at The Belvedere comprise the construction of a new two storey classroom block with additional catering facilities for pupils; internal alterations to form 2 science labs, a new netball court and appropriate external works.
The school has consulted with parents and staff on the expansion and have submitted their business case to the Education and Skills Funding Agency (ESFA) for approval. Subject to ESFA and Cabinet approval works will commence in spring 2019 with the aim of having the building available for occupation by September 2019.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Expansion of The Belvedere Academy (E/11)Report | 6 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.