Cabinet 2010/21 approved this item on Friday 8 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved. H/4
CABINET
MOSSLEY HILL WARD PUBLIC E/12
Cabinet Member: Councillor Barbara Murray Cabinet Member – Education
Director: Steve Reddy, Director - Childrens & Young Peoples Services
Purpose of Report: Award of Construction Contract for expansion of Sudley Junior School
Date: Report No: 8th February 2019 CHS/08/19
Decision Type: Cabinet Key Decision
Executive Summary: In order to meet the demand for primary school places there is a need to expand provision in a number of schools across the City. Sudley Infants has already expanded by 1 form of entry and the proposal to expand the Juniors, also by 1 form of entry has been agreed following consultation. The first cohort coming through the Infants will reach the Junior School in September 2020 but works are required to start in 2019 to meet the funding timescales. The expansion requires the construction of a new two storey teaching block comprising of 4 classrooms, toilets and ancillary storage space.
Information: On 16th December 2016 the Cabinet approved a recommendation that –
The City Council publishes statutory proposals to make prescribed alterations:
to enlarge the premises of Sudley Community Junior School to enable the capacity of the school to increase from 360 to 480 phased over four academic years commencing in September 2020. Further information on the background of the above can be found in report number CHS/38/16.
Statutory Notices proposing the increased admission number from 90 to 120 per year group at Sudley Juniors were published on 9th January 2017 and in the absence of objections was approved by the Director of Children’s and Young Peoples Services under powers delegated by Cabinet.
The procurement route of engaging Kier Construction through the SCAPE framework as a ‘design and build’ solution was proposed via a pre- procurement business case which was fully signed off on the 9th November 2016.
Following a period of site investigations and design meetings in consultation with the school, a Planning Application was submitted to the City Council on the 29th June 2018 for the final scheme and this was approved at the Planning Committee Meeting of the 11th December 2018.
The project is fully funded through the City’s Basic Need allocation for 2018- 2020 and forms part of the overall strategy to ensure there are sufficient school places for the City’s expanding pupil population. Works are due to start on site in April 2019 and complete in December 2019.
Recommendation: That –
(i) in respect of works to Sudley Junior School, the City Council sign a Delivery Agreement (construction contract) with Kier Construction (Liverpool) under the Scape Minor Works Framework up to a maximum contract value of £2,054,900. In lieu of a bond, a Parent Company Guarantee is to be provided by the contractor;
(ii) authority be granted for the City Council to commit expenditure up to a value of £2,152,800 to be financed from the City Council’s approved 2018-2020 Basic Need Capital Allocation. The expenditure comprises the total design and construction costs to Kier of £2,054,900 including contract administration fees and project contingency, plus an agreed contribution to the school for additional sports facilities required due to in the increase in pupil numbers and technical support fees to Kier Workplace Services; and
(iii) the City Council’s Capital Programme is amended accordingly and authority is granted to commit the expenditure within the approval. Financial Implications: Capital The capital costs for the project and forecast expenditure is set out below: Capital Costs Forecast Contract Sum £2,054,900 Contribution to school £ 65,000 Kier WPS technical support £ 32,900
Total £2,152,800
Financed by:
BEESJ17- Sudley Jun BN Capacity (current budget) £1,250,000
The shortfall Of £902,800 to be financed from balances on BEPRMFY Basic Need Funding by way of virement to BEESJ17.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of Construction Contract for expansion of Sudley Junior School (E/12)Report | 6 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.