Cabinet 2010/21, Friday 17 May 2019

Paddington Village (Central) – Delivery Update (M/61)

Approved Executive 2 papers

Cabinet 2010/21 approved this item on Friday 17 May 2019. Below is the council's own wording, with the papers it was decided on.

Item127f

Resolved

Paddington Village (PV) is a flagship development scheme sitting at the eastern gateway of the Knowledge Quarter Mayoral Development Zone home to an unrivalled concentration of knowledge economy assets within a city centre setting. The 30-acre site at PV presents a significant opportunity for growth of national significance with a commercial focus on Life Science, Medical and Education and Knowledge industry led development. In September 2017, a report was approved by Cabinet for the Council to deliver the first five projects at PV Central; (i) Infrastructure, (ii) District Heating, (iii) the Spine (Grade A office), (iv) a MSCP and (iv) a hotel. This report provides a general update on those 5 projects and others being delivered on site by other occupiers (Kaplan and Rutherford Cancer Centre). The report also seeks authority to commit pre-construction expenditure against new projects and seeks authority to update the capital programme in-line with the current net present value (NPV) model for PV Central.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 13 pages

CABINET

KENSINGTON & FAIRFIELD WARD PARTIAL EXEMPTION M/61

Cabinet Member: Joe Anderson OBE Mayor of Liverpool

Director: Nick Kavanagh, Director – Regeneration & Economy

Report Title: Paddington Village (Central) – Delivery Update

Date: Report No: 17 May 2019 EDR/32/19

Decision Type: Cabinet Key Decision

Executive Summary: Paddington Village (PV) is a flagship development scheme sitting at the eastern gateway of the Knowledge Quarter Mayoral Development Zone home to an unrivalled concentration of knowledge economy assets within a city centre setting. The 30-acre site at PV presents a significant opportunity for growth of national significance with a commercial focus on Life Science, Medical and Education and Knowledge industry led development.

In September 2017, a report was approved by Cabinet for the Council to deliver the first five projects at PV Central; (i) Infrastructure, (ii) District Heating, (iii) the Spine (Grade A office), (iv) a MSCP and (iv) a hotel.

This report provides a general update on those 5 projects and others being delivered on site by other occupiers (Kaplan and Rutherford Cancer Centre). The report also seeks authority to commit pre-construction expenditure against new projects and seeks authority to update the capital programme in- line with the current net present value (NPV) model for PV Central. Information: Since the launch of Paddington Village by the Mayor in June 2016, as part of the launch of the International Festival of Business (IFB) and, the adoption of a Spatial Regeneration Framework (SRF) in January 2017 to act as the development framework for PV, development on the site has progressed with significant momentum.

Progress on a scheme-by-scheme basis is summarised below:

Schemes currently on site (or imminently on site in 2019):

Infrastructure Works (including Plot 4 energy centre)

The infrastructure works comprise site wide highways improvements, an undercroft access tunnel, groundwork remodelling and retaining structures (to create development plot plateaus), drainage and attenuation, incoming services, service diversions and the primary construction of some of the public realm.

The works are being delivered over five phases with Phase 1 complete and Phase’s 2, 3 and 4 completing in late-2019. Some of the work packages have been re-phased since the scheme commenced to create more efficient and practical working methodologies on site and, the majority of Phase 5 will now be completed under construction contracts for Plot 3 (the Spine) and Plot 10 (the hotel) as they are structurally interdependent. This report and the amended capital programme also includes a Phase 6 to complete the finishes to the public realm in the main central space in the centre of the development plots.

The Grant Funding Agreement (GFA) for the Combined Authority (CA) Single Investment Fund (SIF) funding of £12m was signed in February2019. Authority to accept the funding was approved in the September 2017 report to cabinet.

District Heating – Combined Heat and Power (CHP)

PV Central will be serviced by a District Heating Network (DHN) from a local Combined Heat and Power (CHP) plant providing a sustainable heating and power source. A separate report specifically on the DHN was approved by Cabinet on 26 April 2019.

Following procurement, Vital Energi were appointed as the Design and Build (D&B) contractor and Operate and Maintain (O&M) contractor. The first contract will be awarded in early-May and works will commence on site in mid-May 2019. The Council are now working with end-users to negotiate heat supply agreements and, are preparing a business case to establish an Energy Services Company (ESCo). Plot 1 - Kaplan International

Following disposal of the plot to Kaplan, Kier Construction are on site building the new international college that will recruit 800 students from 40 countries to Liverpool and represent nearly 50% of the University of Liverpool’s international recruitment into first year programmes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 1 pages Download
PDF
Paddington Village (Central): Delivery Update (M/61)Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Paddington Village (Central) – Delivery Update (M/61)This decision
  2. District Heating Network at Paddington Village (M/60)Decided
  3. Paddington Village Infrastructure - Phase 3 (M/50)Approved
  4. Paddington Village Infrastructure Phase 2 (M/14)Decided
  5. Approval of use of Compulsory Purchase Powers for Paddington Village (RTC/47)Approved
  6. Paddington Village – Spatial Regeneration Framework – Final (RTC/35)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies