Cabinet 2010/21, Friday 7 June 2019

Professional Services for Design and Options Appraisal/ Business Case Support (STA/1)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 7 June 2019. Below is the council's own wording, with the papers it was decided on.

Item133b

Resolved

There are currently 3 professional design contracts in place for Highways and Transportation, which expire at various intervals over the next two months. These contracts were established, at the end of the Amey highways contract, through existing national frameworks, originally for a 12 month period. There is a need to extend these for a further period of up to 12 months and to include a 4th supplier, in order to allow a continuation of the design service. There is also a need for Liverpool City Council to establish its own professional design framework in order for future contracts to be awarded to a pool of high quality suppliers at short notice and in a compliant manner.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 6 pages

CABINET

CITY PUBLIC/EXEMPT STA/1

Cabinet Member: Councillor James Noakes, Cabinet Member – Streetscene, Transport & Highways, Air Quality

Director: Nick Kavanagh, Director Regeneration & Economy

Report Title: Professional Services for Design and Options Appraisal/ Business Case Support

Date: Report No: 7 June 2019 EDR/31/19

Decision Type: Cabinet Key Decision

Executive Summary: There are currently 3 professional design contracts in place for Highways and Transportation, which expire at various intervals over the next two months. These contracts were established, at the end of the Amey highways contract, through existing national frameworks, originally for a 12 month period. There is a need to extend these for a further period of up to 12 months and to include a 4th supplier, in order to allow a continuation of the design service. There is also a need for Liverpool City Council to establish its own professional design framework in order for future contracts to be awarded to a pool of high quality suppliers at short notice and in a compliant manner.

Information:

Background Professional Services, supporting the design process, were provided by Amey Consulting up to the 31st January 2018. When this contract ended, the City Council needed to source the provision of the services from an alternative supplier as soon as possible in order to progress with the delivery of the Transportation Capital Programme.

The original intention was to appoint a minimum of 3 suppliers to provide the design service through the ESPO 2664 Framework. Following a further competition process, with the stated aim of awarding to a minimum of three contractors, only one viable bid was received. A further two suppliers were then sought via alternative frameworks.

Between April and June last year, 3 professional services contracts were established with 3 professional design consultants, these were: - Amey OW (ESPO Framework) which expires on the 16th April 2019 for S38/S278 support and 23rd May 2019 for general design and supervision support. - AECOM (SCAPE Framework) which expires on the 10th June 2019 for general design and supervision support. - Mott McDonalds (CCS Framework) which expires on 22nd Feb 2020

The services these contracts currently supply to Highways are:  Both preliminary and detailed design of relatively small scale highways schemes such as cycle schemes; junction improvements; road safety improvements such as traffic calming; pedestrian crossings; lighting; drainage; structural design, and maintenance.  General highway related professional services including; topographical services, traffic counts; traffic modelling; and other surveys.  Development of outline and full major scheme business cases.

The annual value of these contracts was estimated to be £374,000 based on the previous year’s spend, the actual spend over this period was £6.8m

Due to the amount of work currently being undertaken by the 3 current suppliers, the increased Transportation Capital Programme, and the lack of capacity with current suppliers, it is agreed that a 4th supplier would be beneficial. Given the existing indirect relationship with WSP, (through existing contractors on the design and build contracts), it is proposed that through the CCS Framework, WSP be awarded a 12 month contract for professional services.

The estimated value of works to go through these contracts over the next 12 months is approximately £5m, which includes significant business case development, and works to prepare and manage the demolition of Churchill Way Flyovers.

Proposed New Framework

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Professional Services for Design and Options Appraisal/ Business Case Support (STA/1)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Professional Services for Design and Options Appraisal/ Business Case Support (STA/1)This decision
  2. Professional Consultancy Services - Framework Agreement (LS&C/03)Agreed
  3. Professional and Property Services Partnership - Appointment of DirectorDecided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies