Capital Programme 2018/19 - Final Outturn Position

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 7 June 2019. Below is the council's own wording, with the papers it was decided on.

Item134a

Resolved

During the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of the relevant budgetary position and any relevant actions arising. This report summarises matters of relevance for the twelve-month period and provides information on the final outturn for the budget.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 10 pages

Recommendations

That Cabinet –

(i) note that the outturn of capital expenditure for 2018/19 is £207.773M. This compares against the February 2019 forecast and approved budget of £272.540M;

(ii) note that the capital programme is financed having regard to the available resources and in accordance with the overarching principles set out in the Capital Strategy Statement approved in March 2018 so that the requirement for borrowing is minimised wherever possible;

(iii) note that during March, the final month, £42.664M worth of expenditure was incurred, which represents 21% of the total spend for the year; and

(iv) approve the Capital Programme for 2019/20 to 2023/24 reflecting the carry forward of £61.926M of capital commitments from 2018/19 along with the associated funding.

Background

Capital programme monitors are produced for each month of the financial year with a final outturn report in June setting out the final spend and financing position for the year. This report is the capital programme outturn report for 2018/19.

The Capital Strategy Statement 2018/19 to 2022/23 was approved by City Council on 7th March 2018. This included indicative allocations of capital grants for 2018/19 to 2022/23. Further reports have been approved during the year including the more recent Capital Strategy report presented to Cabinet on the 22nd February 2019 and subsequently ratified by Full Council on 6th March 2019.

After accounting for rescheduling, projects carried forward to 2019/20 and approval of additional resources the final 2018/19 programme spend has amounted to £207.773M.

The City Council will continue to identify future funding streams that are available to both itself and private developers to promote on-going regeneration and investment whilst contributing to the delivery of the Inclusive Growth Plan, the Mayoral Pledges and the City’s Vision, Aims and Priorities.

4. Capital Expenditure Outturn for 2018/19

Table 1 below shows the capital expenditure outturn for 2018/19 compared to the approved period 11 budget. It should be noted that an under spend variance on schemes can represent slippage into a future year rather than a scheme being delivered for less than budget, and the funding available.

Table 1: 2018/19 Approved Capital Expenditure Budget compared to Outturn

Budget approved Capital Outturn 31 Variance at period 11 March 2019 (under) / over spend £000 £000 £000 Capital Expenditure: Planning and Transportation 57,939 50,919 (7,020) Regeneration Developments 122,847 86,081 (36,766) Adult Social care and Health 26,470 23,628 (2,842) Schools and Education 16,368 12,122 (4,246) Leisure 12,349 11,700 (649) Environment 4,763 1,390 (3,373) Housing and Neighbourhood 13,136 9,661 (3,475) Resources 766 435 (331) Corporate 17,902 11,835 (6,067) Total Capital Expenditure 272,540 207,773 64,767

The table identifies that capital expenditure at 31 March 2019 is £64.767M lower than previously budgeted for. The significant variances are set out as follows:

Planning & Transportation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2018/19: Final Outturn PositionReport 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Capital Programme 2018/19 - Final Outturn PositionThis decision
  2. Corporate Risk Register Deep Dive - CR2 Capital ProgrammesAgreed
  3. Capital Programme 2019/20 - Final Outturn PositionDecided
  4. Capital Programme Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Capital Programme Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Capital Programme Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies