Resolved
Resolved that the report be noted.
Audit and Governance Select Committee 2019/20 noted this item on Thursday 13 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the report be noted.
That Cabinet –
(i) note that the outturn of capital expenditure for 2018/19 is £207.773M. This compares against the February 2019 forecast and approved budget of £272.540M;
(ii) note that the capital programme is financed having regard to the available resources and in accordance with the overarching principles set out in the Capital Strategy Statement approved in March 2018 so that the requirement for borrowing is minimised wherever possible;
(iii) note that during March, the final month, £42.664M worth of expenditure was incurred, which represents 21% of the total spend for the year; and
(iv) approve the Capital Programme for 2019/20 to 2023/24 reflecting the carry forward of £61.926M of capital commitments from 2018/19 along with the associated funding.
Capital programme monitors are produced for each month of the financial year with a final outturn report in June setting out the final spend and financing position for the year. This report is the capital programme outturn report for 2018/19.
The Capital Strategy Statement 2018/19 to 2022/23 was approved by City Council on 7th March 2018. This included indicative allocations of capital grants for 2018/19 to 2022/23. Further reports have been approved during the year including the more recent Capital Strategy report presented to Cabinet on the 22nd February 2019 and subsequently ratified by Full Council on 6th March 2019.
After accounting for rescheduling, projects carried forward to 2019/20 and approval of additional resources the final 2018/19 programme spend has amounted to £207.773M.
The City Council will continue to identify future funding streams that are available to both itself and private developers to promote on-going regeneration and investment whilst contributing to the delivery of the Inclusive Growth Plan, the Mayoral Pledges and the City’s Vision, Aims and Priorities.
4. Capital Expenditure Outturn for 2018/19
Table 1 below shows the capital expenditure outturn for 2018/19 compared to the approved period 11 budget. It should be noted that an under spend variance on schemes can represent slippage into a future year rather than a scheme being delivered for less than budget, and the funding available.
Table 1: 2018/19 Approved Capital Expenditure Budget compared to Outturn
Budget approved Capital Outturn 31 Variance at period 11 March 2019 (under) / over spend £000 £000 £000 Capital Expenditure: Planning and Transportation 57,939 50,919 (7,020) Regeneration Developments 122,847 86,081 (36,766) Adult Social care and Health 26,470 23,628 (2,842) Schools and Education 16,368 12,122 (4,246) Leisure 12,349 11,700 (649) Environment 4,763 1,390 (3,373) Housing and Neighbourhood 13,136 9,661 (3,475) Resources 766 435 (331) Corporate 17,902 11,835 (6,067) Total Capital Expenditure 272,540 207,773 64,767
The table identifies that capital expenditure at 31 March 2019 is £64.767M lower than previously budgeted for. The significant variances are set out as follows:
Planning & Transportation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital OutturnReport | 10 pages | DownloadRead as text |
Follow Audit and Governance Select Committee 2019/20 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Feb 2020 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 28 January 2020 be approved. | Approved | Open |
| 24 Feb 2020 | Estimated Collection Fund Outturn 2019/20 & Statements of Chief Financial Officer on Robustness of Estimates 2020/21 and Adequacy of Provisions & Reserves 2020/21Resolved that the Estimated Collection Fund Outturn 2019/20 and Statements in respect of the Robustness of the Estima... | Noted | Open |
| 28 Jan 2020 | Minutes of the Last Meeting - 5 December 2019Resolved that the minutes of the meeting held on 5 th December 2019 be approved. | Approved | Open |
| 28 Jan 2020 | Mayor UpdateResolved that the update be noted. | Noted | Open |
| 28 Jan 2020 | Grant Thornton UpdateResolved that – (i) the update report be noted; and (ii) the thanks of the Committee be extended to Robin Baker in re... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.