This report updates Cabinet on the Festival Gardens project following previous Cabinet reports of 2nd April 2015 (RTC27), 10th June 2016 (RTC/4), 16th June 2017 (EDR/21/17), 23rd February 2018 (EDR/61/17), 12th October 2018 (EDR/73/18) and 6th December 2019 (EDR/63/19). This reports seeks authority to finalise and complete a Grant Funding Agreement with the Liverpool City Region (LCR) Combined Authority for pre-development SIF grant funding towards the undertaking of pre-remediation material processing trials at Festival Gardens, and to accept £150,000 of pre-development SIF grant funding.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
A report was presented to Cabinet on 6th December 2019, requesting authority to: (i) negotiate and agree an Master Land Agreement (MLA) and Phase Lease with IMGF Developments Ltd, (ii) negotiate and agree a grant funding agreement with Homes England and the LCR Combined Authority, and (iii) undertake the design of a remediation strategy and procurement of a remediation contractor.
Cabinet Report (EDR/63/19) set out how the Council has conditional grant funding offers from Homes England and LCR Combined Authority to fund the site remediation, and potentially deliver site infrastructure. Draft Heads of Terms (HOTs) for a tripartite Grant Funding Agreement (GFA) have been negotiated between parties, and Cabinet delegated authority to the Director of Regeneration & Economy, Director of Finance & Resources and the City Solicitor to negotiate and complete a Tripartite GFA. A further report would be brought to Cabinet, once this position was confirmed.
It was also acknowledged in this Report that the LCR Combined Authority had given approval in principle to assist in funding a £150k contribution towards the pre-remediation material processing trials, on the basis that this will provide greater certainty on ground conditions and material processing efficiency, and in turn reduce cost-risk. However, conditions of this separate funding source were unknown at this time, and therefore a further report would need to be brought to Cabinet in this respect.
This report sets out the progress made by the Council in undertaking a pre- remediation material processing trial of 1,000 cubic metres to inform the forthcoming detailed remediation strategy, and the various benefits this has.
2. Pre-remediation Material Processing Trial
Delegated Authority (DT/59/19) was granted to procure Vinci, Arup and Kier Business Services to design and manage pre-remediation material processing field trails and site preparation, and to provide geo-technical and costs consultancy support services. This involved material processing trials of 1,000 cubic metres in 5 locations across the Development Zone, capturing a range of ground conditions, established through the site investigation undertaken to date. The objectives of the trials are to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.