This report seeks approval to amend the value of the proposed interest free loan amount approved at Cabinet on 6 th March 2020 under report EDR/87/19 by increasing it to £9m. The original report approved a further £9.5m investment (£9m Capital & £0.5m Revenue) in the street lighting infrastructure that included an interest free loan of £7.9m from Salix Finance Ltd. The amended value of the loan is equal to the value of the capital element of the investment approved.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Cabinet Member: Cabinet Member for Regeneration & Highways
Director: Director for Regeneration & Economy
Report Title: Street Lighting – LED Implementation & Energy Saving Programme Update
Date: Report No: 7th May 2020 EDR/30/20
Decision Type: Key Decision
Executive Summary: This report seeks approval to amend the value of the proposed interest free loan amount approved at Cabinet on 6th March 2020 under report EDR/87/19 by increasing it to £9m.
The original report approved a further £9.5m investment (£9m Capital & £0.5m Revenue) in the street lighting infrastructure that included an interest free loan of £7.9m from Salix Finance Ltd.
The amended value of the loan is equal to the value of the capital element of the investment approved.
Information: The original value of the investment and the estimated savings for this project remain unchanged but following the initial application to Salix Finance Ltd. a recalculation of the loan amount was undertaken, based on works phasing over financial years. As a result of this Salix Finance Ltd have advised they could potentially provide a loan for the full amount of the capital element of the investment of £9m.
The final loan value will need to be recalculated once the tender exercise has
V1.1/060919 – 170919 onwards been completed and costs can be confirmed and hence officers will require delegation of the power to amend the final loan amount to reflect the costs of the project and what Salix Finance Ltd is prepared to offer.
Recommendation: That –
(i) approval be granted to the Director of Regeneration & Economy, in consultation with the City Solicitor and the Director of Finance & Resources, to submit a loan application for up to £9m interest free loan to Salix Finance Ltd and, subject to the loan being offered to the Council on acceptable terms, approval be granted for the Council to enter into the loan agreement;
(ii) delegated authority be granted for the Director of Regeneration & Economy, in consultation with the City Solicitor, to negotiate the final amount of the loan from Salix Finance Ltd and to vary the amount referred to in paragraph 1 above to reflect actual costs of the project and amount of loan being offered; and
(iii) the Capital Programme be amended to reflect the additional funding and work streams detailed in the report submitted, subject to the final agreed loan amount.
Financial Implications: The impact of the increased loan amount is to reduce the prudential borrowing required for the project. The savings from the original report remain unchanged.
The below table overleaf provides an overview of the financials for this project: Street Lighting Phase 3,4,5 financials
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Total 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 £M's £M's £M's £M's £M's £M's £M's £M's Capital Expenditure financing analyis
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Total 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 £M's £M's £M's £M's £M's £M's £M's £M's Revenue Implications
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.