CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Cabinet, Tuesday 5 May 2026

Microsoft Enterprise Subscription Agreement

Agreed Executive 3 papers

AI summaryLiverpool City Council Cabinet approved a three-year Microsoft licensing contract worth £12 million starting July 2026, and increased its ICT Framework value by £6.5 million.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThree-year Microsoft licensing deal awarded to Bidder B
Money£12,000,000 (exc VAT)Plus £6,500,000 (exc VAT) framework variation
What happens nextContract starts 1 July 2026Three-year term via ICT Framework
Who it affectsAll council services and wardsUnderpins systems used citywide

What was decided

Cabinet approved a three-year Microsoft licensing and professional services contract to Bidder B via the ICT Framework, at an estimated cost of £12,000,000 (exc VAT), commencing July 2026. Report P2, 6.1

Cabinet approved a variation to the ICT Framework increasing its total value by £6,500,000 (exc VAT), bringing the overall framework value to £19.5m (exc VAT). Report P2, 1.17, 1.21

Why

The current Microsoft contract DN657205 expires on 30 June 2026, and the Council is wholly dependent on Microsoft products for day-to-day operations including email, security, remote working and the intranet. Report 1.12, 2.1, 1.1

Using the ICT Framework delivered a saving of £853k (exc VAT) compared with the Crown Commercial Service Microsoft Aggregation route, and offered enhanced social value commitments. Report 1.14, P19

Continued investment supports the Council's Digital, Data and Technology Strategy and the new Enterprise Resource Platform finance and operations solution. Report 1.7, 1.11

What happens next

The new contract commences on 1 July 2026 and runs for three years, funded from the approved ICT and Digital revenue budget. Report 6.1, 6.3, 1.12

Officers must ensure all contractual details, schedules and specifications are accurately completed prior to signature, and a formal deed of variation must be completed for the framework change. Report 7.4, 7.8

Spend against the ICT Framework will be closely monitored to ensure sufficient headroom for other software requirements. Report 1.18

The money

  • £12,000,000 (exc VAT) Estimated three-year Microsoft licensing contract cost Report P2, 6.1
  • £6,500,000 (exc VAT) Increase to the ICT Framework value Report P2, 1.17, 1.21
  • £19.5m (exc VAT) New total value of the ICT Framework after variation Report 1.17
  • £13m (exc VAT) Original ICT Framework award value in June 2025 Report 1.15, 1.16, 1.21
  • £853k (exc VAT) Saving from using ICT Framework instead of CCS Microsoft Aggregation Report 1.14
  • £597k (exc VAT) Spend to date against the framework as of March 2026 Report 1.15
  • £403k (exc VAT) Available contract value remaining after the Microsoft award Report 1.15

Options considered

  • Chosen: Award contract via the ICT Software and Professional Services Framework to Bidder B. Best value, saving of £853k (exc VAT) compared with CCS Aggregation, and enhanced social value commitments Report 1.14, P19
  • Rejected: Use the Crown Commercial Service Microsoft Aggregation route. More expensive than the ICT Framework Report 1.14, P19
  • Rejected: Re-tender a new software framework to cover the Microsoft requirement. Would require significant resource and time, far exceeding the effort of a permitted variation Report 3.3
  • Rejected: Move away from Microsoft products. No proven credible alternative at this time, and any switch would take years and could not be concluded before a new agreement is required Report 3.1, 3.2

Implications

  • Financial: Contract cost will be funded from the approved ICT and Digital revenue budget, with budget growth included in the 2025/26 budget on a recurrent basis to cover higher future licence costs. Report 6.3
  • Legal: Award via the ICT Framework is compliant with PCR 2015 Regulation 33(8)(c), and the 50% value variation is permitted under Regulation 72(1)(b). Report 1.19, 1.20, 7.5, 7.7
  • Legal: Council has legal power to enter the contract and vary the framework under section 1 of the Localism Act 2011 (general power of competence). Report 7.1
  • Risk: Without a viable framework with sufficient value, ICT procurement operations would be impacted and major projects and programmes halted. Report 2.2
  • Equalities: A full Equality Impact Assessment was not required; the renewal continues an existing service with no foreseeable equality or diversity impact. Report 4.1
  • Other: Social value commitment from Bidder B of four donated end-user devices per £50k of expenditure, equating to approximately 960 device donations for digitally excluded service users. Report 4.3

Who and where

  • All Liverpool City Council staff and services that use Microsoft products for email, security, remote working and the intranet Report 1.1, P5
  • All wards across the city, as Microsoft products underpin systems used across council services Report P5
  • Digitally excluded service users in the community who will receive donated end-user devices Report 4.3
  • Residents engaging digitally with the Council, supported by Microsoft platforms underpinning democratic services Report 4.4

Timeline

  • June 2025: Original ICT Framework awarded at £13m (exc VAT) Report 1.15, 1.16
  • March 2026: Spend to date against the framework reached £597k (exc VAT) Report 1.15
  • 30 June 2026: Current Microsoft contract DN657205 expires Report 1.12
  • 1 July 2026: New three-year Microsoft Enterprise Subscription Agreement commences Report 6.1, 1.12

Plain English for the jargon

  • ICT Framework: The Council's ICT Software and Professional Services Framework used as a route to market for software and professional services.
  • LSP: Microsoft Licencing Solution Partner, the authorised intermediary required to transact under Microsoft's Volume Licencing model.
  • CCS Microsoft Aggregation: A procurement route run by the Crown Commercial Service, tested as an alternative to the ICT Framework.
  • SPA24: Strategic Partnership Arrangement 2024, Microsoft's discounted public-sector pricing arrangement covering M365, Azure and AI products.
  • PCR 2015: Public Contract Regulations 2015, governing procurement procedures and framework variations.
  • ERP: Enterprise Resource Platform, the Council's new finance and operations solution underpinned by Microsoft products.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item189

Resolved

It was resolved that Cabinet agreed – 1. Approved the award of a three-year contract, via the Council’s ICT Framework to Bidder B (as identified in Appendix 2) for the provision of Microsoft licencing and associated professional services commencing in July 2026 for a period of three years at an estimated cost of £12,000,000 ( exc VAT). 2) 2. Approved a variation to the ICT Framework to increase the total value by £6,500,000 ( exc VAT) to allow for continued use of this route to market for other Council software requirements.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in this report, Cabinet is recommended to:

1) Approve the award of a three-year contract, via the Council’s ICT Framework to Bidder B (as identified in Appendix 2) for the provision of Microsoft licencing and associated professional services commencing in July 2026 for a period of three years at an estimated cost of £12,000,000 (exc VAT). 2) Approve a variation to the ICT Framework to increase the total value by £6,500,000 (exc VAT) to allow for continued use of this route to market for other Council software requirements.

Decision Status

This is a key decision by virtue of expenditure in excess of £500k.

The decision supports Pillar 6 of the Council Plan – “A Well-Run Council”. Microsoft licencing provides staff with the modern tools required to communicate, collaborate and deliver efficient, high-quality services. The decision has citywide impact, as Microsoft products underpin the systems and applications used across all Council services and all wards.

Ongoing use of the ICT Software and Professional Services Framework will also ensure that Council officers continue to have timely and cost-effective access to the software tools essential for service delivery.

1. Background and Context

1.1Microsoft technologies are embedded across everyday Council operations, enabling staff to communicate effectively with colleagues, partners and residents. Microsoft software supports email, security, remote working and the Council’s intranet. It also integrates with key line-of-business systems such as SAP, Liquidlogic, and many corporate applications.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet Report Appendix: Evaluation Award OutcomeAppendix 1 153 KB Download
PDF
Equality Impact Assessment: Microsoft AgreementAppendix 3 309 KB Download
PDF
Microsoft Enterprise Subscription AgreementReport 202 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
LR
Councillor Liam RobinsonLeader of the Council, present
DB
Councillor Daniel BarringtonCabinet Member, present
RB
Councillor Ruth BennettCabinet Member, present
AC
Councillor Angela ColemanCabinet Member, apologies
HD
Councillor Harry DoyleCabinet Member, present
LP
Councillor Liz ParsonsCabinet Member, present
LR
Councillor Laura Robertson-CollinsCabinet Member, present
NS
Councillor Nick SmallCabinet Member, present
HW
Councillor Hetty WoodCabinet Member, present
JK
Councillor Joanne KennedyCabinet Member, present

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open