AI summaryLiverpool Cabinet approves Derwent Development Management to manage £3.4m redevelopment of Kensington Fields Community Centre, funded by a charity-paid lease premium.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDDML appointed as development manager
Money£3.4m plus VATCapital works funded by lease premium
What happens nextFinalise and sign agreementsCorporate Director to complete terms
Who it affectsKensington and Fairfield wardKFCA and local community users

What was decided

Cabinet appointed Derwent Development Management Limited (DDML) as development manager for the redevelopment of the Kensington Fields Community Centre, with a direct award exempt from competition. Report P2, 1.8

Cabinet varied the previously approved property transactions so the Council directly commissions the £3.4m of works, recouped through a new 125-year lease premium paid by KFCA using Albert Gubay Foundation funding. Report 1.3, 1.16, 2.3

Cabinet approved delegated authority to the Corporate Director for City Development, with the Corporate Director of Finance, to finalise terms and enter into the agreements. Report P2

Why

The Albert Gubay Foundation will only fund KFCA if DDML, its connected company, manages the project, so a competitive tender is not possible and the Council must appoint DDML directly. Report 1.5, 1.6, 1.14, 7.8

Having the Council commission the works allows it to recover VAT, maximising the value of the charitable donation spent on the building. Report 1.7, 2.2, 6.1

Doing nothing would reduce available capital investment and risk delay-driven cost increases that could put the whole project at risk. Report 3.1, 1.12

What happens next

The Corporate Director for City Development, in consultation with the Corporate Director of Finance, will finalise detailed terms and enter into the development agreement, lease and supporting documents. Report P2

Contractual safeguards will be put in place, including a fixed and capped cost under the development agreement, liquidated damages for lost rental income, collateral warranties, and an Agreement for Lease with KFCA. Report 1.9, 1.10, 1.16

The money

  • £3.4m plus VAT Current cost estimate for the community centre redevelopment scheme Report 1.2
  • £3.4m Value of capital works to the community centre, to be added to the capital programme Report P2, 6.1
  • £600,000 Undervalue of the disposal as set out in the previous January 2025 Cabinet report, within the £2m general consent threshold Report 7.1
  • £500,000 Threshold exceeded making this a key decision (development agreement and lease consideration both above this level) Report P4
  • £5,193,000 inclusive of VAT Current statutory procurement threshold, above which the Procurement Act 2023 procedures apply; the contract is below this Report 7.7

Options considered

  • Chosen: Enter the revised arrangements with DDML directly, funded by an AGF-backed lease premium. Maximises investment into the building, allows VAT recovery, and is the only way to access the AGF funding. Report 1.3, 1.7, 2.2, 2.3
  • Rejected: Do nothing and keep the original 25 January 2025 Cabinet approval unchanged. Would give an inefficient delivery structure, reduce capital investment, and risk project failure through value engineering delays. Report 3.1

Implications

  • Financial: The £3.4m capital programme entry will be funded by a capital receipt from the lease premium; VAT recovery is constrained by the Council's Partial Exemption limit and kept under close scrutiny. Report 6.1, 6.2, 6.3
  • Legal: External tax and subsidy control advice concluded the transaction is lawful and compliant, though HMRC may review it; specialist advice on reducing risk will be implemented. Report 7.3, 7.12, 7.13
  • Legal: A Contracts Standing Order exemption under rule 7.2.2 is granted on the basis that the services are specialist and cannot be competitively priced because only DDML is permitted by the funder. Report 1.14, 7.8
  • Risk: Full construction, cost-overrun and time-overrun risk sits with DDML, who are wholly controlled by the Albert Gubay Foundation; the Council can step in if the development agreement terminates. Report 1.9, 1.16
  • Equalities: An Equality Impact Assessment screening found the decision is anticipated to be neutral on all protected characteristic groups, socio-economic status and care experience. Report 4.1, P33
  • Climate: The redeveloped centre must comply with relevant planning legislation; compliance with minimum environmental efficiency standards was a pre-condition for the new lease. Report 1.1, 4.2

Who and where

  • Kensington Fields Community Association (KFCA) as occupier and leaseholder of the centre Report 1.1, 1.3, P5
  • Residents and community users in Kensington and Fairfield ward Report P4, P5, 1.15
  • Ward members, who have been consulted and support the investment Report 5.1
  • Albert Gubay Foundation as the charitable funder (via KFCA, not the Council directly) Report 1.2, 1.6, 1.15
  • Derwent Development Management Limited as development manager Report 1.5, 1.8

Timeline

  • 31 May 2013: The existing licence agreement with KFCA expired (occupancy has continued since) Report 1.1
  • 21 January 2025: Cabinet previously approved property arrangements to facilitate AGF investment into the centre Report P32, 7.1
  • November 2025: Planning application for the redevelopment was submitted Report 1.2
  • 5 May 2026: Cabinet approved the revised contractual arrangements, including DDML's appointment and the £3.4m capital programme amendment
  • 125 years: Length of the new lease to KFCA, with the premium payable in full on completion Report 1.3

Plain English for the jargon

  • DDML: Derwent Development Management Limited, the development arm of the Albert Gubay Foundation
  • KFCA: Kensington Fields Community Association, the charity occupying the community centre
  • AGF: Albert Gubay Foundation, a registered charity funding the redevelopment through KFCA
  • Partial Exemption (PE) Limit: A VAT rule limiting how much VAT on exempt activities the Council can recover, set at 5% of total VAT recovery
  • CSO exemption (rule 7.2.2): Contracts Standing Order exemption used when services are of a specialist nature and competitive prices cannot be obtained
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item194

Resolved

It was resolved that Cabinet – 1. Granted authority for the appointment of Derwent Development Management Limited as development manager for the proposed redevelopment of the Kensington Fields Community Centre on the main terms outlined in the body of the report. 2. Granted an exemption pursuant to rule 7.2.2 of the Contracts Standing Order exempting the above contract award from the competition requirements under the Contracts Standing Orders, on the grounds that the contract concerns services of a specialist nature such that competitive prices cannot be obtained, for the reason set out in the main body of this report. 3. Granted authority for variations to the previously approved property transactions as set out in the body of the report (see paragraph 1.15). 4. Approved the amendment to the capital programme to reflect the value of capital works to the community centre (£3.4m) undertaken by the developer, to be funded by capital receipts obtained from the lease premium set out in the leasing agreement 5. Approved the delegated authority to the Corporate Director for City Development, in consultation with the Corporate Director of Finance, to finalise the detailed terms of the agreements and enter into the agreements required to implement this decision.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in this report, Cabinet is recommended to:

1) Grant authority for the appointment of Derwent Development Management Limited as development manager for the proposed redevelopment of the Kensington Fields Community Centre on the main terms outlined in the body of the report. 2) Grant an exemption pursuant to rule 7.2.2 of the Contracts Standing Order exempting the above contract award from the competition requirements under the Contracts Standing Orders, on the grounds that the contract concerns services of a specialist nature such that competitive prices cannot be obtained, for the reason set out in the main body of this report. 3) Grant authority for variations to the previously approved property transactions as set out in the body of the report (see paragraph 1.15). 4) Amend the capital programme to reflect the value of capital works to the community centre (£3.4m) undertaken by the developer, to be funded by capital receipts obtained from the lease premium set out in the leasing agreement 5) Delegate authority to the Corporate Director for City Development, in consultation with the Corporate Director of Finance, to finalise the detailed terms of the agreements and enter into the agreements required to implement this decision.

Decision Status

This is a key decision by virtue of the procurement of the Development Agreement and the consideration for the lease which are both in excess of £500,000. The proposed decision contributes to Pillar 1, 3 and 6 of the Council Plan by virtue of providing significant inward investment into the built environment through a charitable donation from a long standing and well-established charity. The investment will create a step change in the provision of community services within the Kensington and Fairfield ward from a new building, delivered by an established community group, the KFCA.

The proposed decision impacts Kensington and Fairfield ward within the city.

1. Background and Context

Kensington Fields Community Centre

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Change in Contractual Arrangements for lease to Kensington Fields Community AssociationReport 224 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
LR
Councillor Liam RobinsonLeader of the Council, present
DB
Councillor Daniel BarringtonCabinet Member, present
RB
Councillor Ruth BennettCabinet Member, present
AC
Councillor Angela ColemanCabinet Member, apologies
HD
Councillor Harry DoyleCabinet Member, present
LP
Councillor Liz ParsonsCabinet Member, present
LR
Councillor Laura Robertson-CollinsCabinet Member, present
NS
Councillor Nick SmallCabinet Member, present
HW
Councillor Hetty WoodCabinet Member, present
JK
Councillor Joanne KennedyCabinet Member, present

On this subject at Liverpool

Search all
  1. Change in Contractual Arrangements for lease to Kensington Fields Community AssociationThis decision
  2. Change in Contractual Arrangements for lease to Kensington Fields Community AssociationDeferred

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open
17 Nov 2026 Violence Against Women and Girls StrategyDecision – a) The Council is a statutory partner in the Community Safety Partnership, Citysafe , it was recommended t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies