Approval of 'Home – A Celebration of Place' - programme of place-based artist commissions

Agreed Executive 3 papers

AI summaryLiverpool Cabinet approves 'Home, A Celebration of Place' artist commissions programme with £500,000 budget for 2026/27, focusing on the most deprived neighbourhoods.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedBudget and implementation of Home programme approved
Money£500,000Recurring three-year programme funding allocation
What happens nextMay 2026 launchRollout begins May 2026; delivery runs to March 2027
Who it affectsAll city wardsCitywide with focus on most deprived 10% areas

What was decided

Cabinet approved the budget and implementation of the 'Home, A Celebration of Place' programme and noted the proposed timeline. Report P2

Cabinet noted the council's planned expenditure of the recurring three-year approved £500,000 programme funding. Report P3

Why

The programme aims to combat isolation, increase cohesion, resilience, integration, safety, trust and belonging by funding place-based artist commissions in neighbourhoods with less access to city centre cultural activity. Report 1.2, 2.1, 2.2

It supports Pillar 3 'Thriving Communities' of the Council Plan and the Culture Makes Liverpool Strategy 2025-2030 priorities around strengthening communities, celebrating place, supporting people, and growing the economy. Report P6, 1.15, 1.16, 1.17, 1.19

The £500,000 was previously approved by Cabinet on 24 February 2026 and Full Council on 4 March 2026 as part of the 2026/27 Budget. Report 6.1

What happens next

Rollout and launch the programme in May 2026, with call-out for commissions and small grants in June 2026, and confirmation of the full programme in July 2026. Report P18, P19, P20

Deliver commissions, micro-commissions, community engagement and outputs from August 2026 to February 2027, followed by a final city centre celebration and legacy, monitoring and evaluation in February-March 2027. Report P20, P21, 1.9

Culture Liverpool will shortlist proposals and present recommendations to a panel of elected members and officers; final funding decisions rest with the appropriate officer under delegated authority. Report 1.34, 1.35, 1.36

The money

  • £500,000 Total programme budget, recurring three-year approved funding Report P3, P50, 6.1
  • £250,000 Large-scale commissions funding pot for artist/arts organisations in minimum five priority locations Report 1.29, 1.32
  • £50,000 Grants funding pot for micro-commission grants of up to £5,000, minimum 10 grants Report 1.30, 1.32
  • £25,000 Final event/celebration in city centre location Report 1.32
  • £50,000 Home Project Manager post (12-month extension of Creative Community Engagement Officer) Report 1.32
  • £50,000 Marketing and communications campaign Report 1.32
  • £40,000 Capacity building and upskilling opportunities Report 1.32
  • £10,000 Accessibility provision Report 1.32
  • £25,000 Contingency Report 1.32

Options considered

  • Rejected: Not to undertake the project. Would perpetuate low engagement and inequality of access to cultural activity and damage the city's reputation as a cultural leader Report 3.1
  • Rejected: Reduce the budget. Would reduce impact, undermine long-term positive effects and reinforce the view that cultural activity is city centre only Report 3.2

Implications

  • Financial: All spend must comply with the council's Financial Regulations, grant-making framework and contract standing orders; no additional financial impacts beyond the approved £500,000 envelope are anticipated. Report 6.2, 6.3
  • Legal: The council relies on the general power of competence under Section 1 of the Localism Act 2011; any transfer of funds must comply with the Subsidy Control Act 2022 and UK procurement legislation. Report 7.1, 7.4, 7.5
  • Equalities: An Equality Impact Assessment has been completed; no negative impacts anticipated and positive impacts identified for race, age, disability, religion/belief and socio-economic status. Report 4.1, 4.4, 4.7
  • Climate: Programme encourages local delivery to reduce travel, promotes active travel options, and aims to integrate climate-focused creative projects aligned with Liverpool's role as a UN Accelerator City. Report 4.9
  • Risk: Risks include budget overshoot from inflation, demand outstripping funding, limited delivery capacity, and reputational risk from inequitable distribution; these will be managed through scalable design and regular financial monitoring. Report 6.5
  • Other: Programme supports the Liverpool Anti-Racism Strategy by fostering belonging and equitable access to opportunity through creative cultural engagement. Report 4.6

Who and where

  • Residents across all wards of Liverpool, with priority focus on the most deprived 10% of neighbourhoods by Indices of Deprivation 2025 Report P7, 1.4
  • Lead artists, freelancers and arts organisations applying for commissions and micro-commission grants Report 1.29, 1.30, 1.33
  • Local community groups, schools, faith organisations, voluntary and community sector partners Report 1.7, 1.20
  • Elected members partnering with artists and communities through local steering groups Report 1.3, 1.7
  • Emerging artists and young people seeking pathways into the cultural sector
  • Local businesses engaged through local procurement and high street footfall Report 1.19, 4.13

Timeline

  • May 2026: Rollout and launch of programme Report P18
  • June 2026: Call-out for commissions and roll-out of small grants programme Report P19
  • July 2026: Confirmation of full programme Report P20
  • August 2026, February 2027: Programme delivery including micro-commissions, community engagement and outputs Report P20
  • February, March 2027: Final collaborative celebration, legacy, monitoring and evaluation Report P21, 1.9

Plain English for the jargon

  • Place-based: Approach targeting investment and activity to specific local neighbourhoods, particularly those identified as most deprived by the Indices of Multiple Deprivation.
  • Micro-commission grant: Small grant of up to £5,000 for small-scale community arts and creative activities, or to enhance an existing local event or festival.
  • IMD (Indices of Multiple Deprivation): Official measure of relative deprivation at a local level, using indicators including health, income and employment; the 2025 release is used to identify priority areas for the programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item188

Resolved

It was resolved that Cabinet agreed – 1. Approved the budget and implementation of the ‘Home – A Celebration of Place’ programme and note the proposed timeline for roll-out and delivery. 2. Noted the Council’s planned expenditure of the recurring three year approved £500,000 programme funding as set out in paragraph 1.32 of this report, ... view the full minutes text for item 188.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in this report, Cabinet is recommended to:

1) Approve the budget and implementation of the ‘Home – A Celebration of Place’ programme and note the proposed timeline for roll-out and delivery.

2) Note the Council’s planned expenditure of the recurring three year approved £500,000 programme funding as set out in paragraph 1.32 of this report, which details the proposed allocation across commissions, grants, staffing, marketing, capacity building and associated delivery costs.

Decision Status

This is a key decision by virtue of both the financial value and affecting more than 2 wards in the city.

The proposed decision contributes to Pillar 3 of the Council Plan, ‘Thriving Communities’ - the programme strengthens local engagement and supports cultural activity directly within neighbourhoods

The proposed decision has potential to impact all wards within the city. The programme is designed to be delivered citywide, ensuring benefits reach communities across every ward.

1. Background and Context

1.1Building on the success of previous Creative Neighbourhood and Creative Communities initiatives, the ‘Home – A Celebration of Place’ programme will fund a programme of artistic commissions and celebrations across the city during 2026/27.

1.2The Home programme will build connections between people from all backgrounds and between communities and neighbourhoods, aiming to combat issues of isolation, increasing cohesion, resilience, integration, safety, trust and belonging.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Home Marketing Plan OverviewAppendix 1 138 KB Download
PDF
Home EqIA FINAL23326Appendix 2 349 KB Download
PDF
Approval of 'Home: A Celebration of Place': programme of place-based artist commissionsReport 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
LR
Councillor Liam RobinsonLeader of the Council, present
DB
Councillor Daniel BarringtonCabinet Member, present
RB
Councillor Ruth BennettCabinet Member, present
AC
Councillor Angela ColemanCabinet Member, apologies
HD
Councillor Harry DoyleCabinet Member, present
LP
Councillor Liz ParsonsCabinet Member, present
LR
Councillor Laura Robertson-CollinsCabinet Member, present
NS
Councillor Nick SmallCabinet Member, present
HW
Councillor Hetty WoodCabinet Member, present
JK
Councillor Joanne KennedyCabinet Member, present

On this subject at Liverpool

Search all
  1. Approval of 'Home – A Celebration of Place' - programme of place-based artist commissionsThis decision
  2. Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)Decided

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open
17 Nov 2026 Violence Against Women and Girls StrategyDecision – a) The Council is a statutory partner in the Community Safety Partnership, Citysafe , it was recommended t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies