24/505235/FULL Land West of Pattenden Lane, Marden, Kent
AgreedPlanning3 papers
AI summaryMaidstone Planning Committee approved a solar farm at Land West of Pattenden Lane, Marden, by 12 votes to 1, subject to conditions and a legal agreement, with amended materials and landscaping conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to conditions and legal agreement
MoneyMonitoring fee to be securedPre-payment of monitoring fee mentioned
What happens nextLegal agreement to be completedAnd planning conditions settled by Head of Development Management
Who it affectsLand West of Pattenden Lane, MardenSolar farm development site
What was decided
Permission was granted for the solar farm, subject to conditions and the prior completion of a legal agreement or planning obligation.
An informative was added requiring white noise machines on construction traffic, and Saturday working hours were changed to start at 0900 instead of 0800.
Delegated powers were given to the Head of Development Management to settle or amend conditions, ensuring the attenuation basin has a wet component and a realistic landscape scheme is delivered.
Why
A new Maidstone Borough Landscape Character Assessment (Update) was published in June 2026 and is a material planning consideration. Report P6
The updated assessment does not change the considerations in the original committee report, but the landscaping condition was amended to reflect the appropriate species mix and new character assessment. Report P7
What happens next
Condition 3 (Materials) was amended to require timber cladding or screening on the substation building facades. Report P9, P11
The landscaping condition now requires a scheme in line with the updated Landscape Character Assessment, including specific native hedgerow species mix and advance planting. Report P13, P14
Options considered
Chosen: Grant permission with amended conditions and informatives. Voted 12 For, 1 Against, 0 Abstentions
Implications
Environment and climate: Solar farm development permitted, subject to landscape and ecological mitigation including native hedgerow planting and an attenuation basin with a wet component. Report P14
Legal: A legal agreement or planning obligation must be completed before the permission takes effect.
Other: Construction traffic must use white noise machines, and Saturday working hours start at 0900 rather than 0800 to reduce local impact.
Who and where
Residents near Land West of Pattenden Lane, Marden Report P3
The applicant for the solar farm development Report P4
Timeline
June 2026: Maidstone Borough Landscape Character Assessment (Update) published Report P6
16 July 2026: Planning Committee granted permission with 12 For, 1 Against, 0 Abstentions
First planting season (October to March) following commencement of development: Advance hedgerow planting to be implemented along the eastern boundary visibility splays Report P14
Plain English for the jargon
PV arrays: Photovoltaic arrays, meaning rows of solar panels that generate electricity from sunlight.
Attenuation basin: A landscaped depression designed to hold and slow rainwater runoff from the site, helping to manage drainage.
Informative: Guidance added to a planning permission that is not a formal condition but gives the applicant advice.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59
Resolved
That permission be granted subject to the conditions and the prior completion of a legal agreement or planning obligation to secure the heads of terms or pre-payment of monitoring fee set out in the report, with; An informative on condition 8 (Construction Management Plan) to include white noise machines on construction traffic; An informative on condition 13 (Hours of Working) to amend the starting hour of working on Saturday from 0800 to 0900; 2. That the Head of Development Management be given delegated powers to be able to settle or amend any necessary planning conditions and/or informatives in line with the matters set out in the recommendation and as resolved by the Planning Committee including ensuring that the attenuation basin had a wet component and that a realistic landscape scheme is delivered. Voting : 12 – For 1 – Against 0 – Abstentions
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Since the publication of the committee report the Maidstone Borough Landscape Character Assessment (Update) June 2026 was published and is a material planning consideration.
The details within the updated document do not change the considerations made in the appraisal set out in the committee report. However, the landscaping condition will be amended to reflect the appropriate species mix set out in the report and reflect the new character assessment as set out below.
Correction to Conditions
Condition 3 (Materials) on page 40 - amend to read:
(Bold – new text Strikethrough = deleted text)
Above ground works shall not commence unless and until details of the proposed layout, materials and finish including colour of all solar panels, frames, ancillary buildings, equipment and enclosures samples of the materials to be used in the construction of the external surfaces of the buildings and structures hereby approved shall be have been submitted to and approved in writing by the Local Planning Authority. Specifically, the substation building shall feature timber cladding or timber screening to the facades. The development shall be carried out in accordance with the approved details and be retained as such for the lifetime of the proposed development.
Reason: To ensure that the finished appearance is visually acceptable 19. Landscaping Scheme
No development shall commence at the site until a fully detailed scheme of landscaping proposals including a timetable for the implementation of all landscaping works and a programme for its management and maintenance have been submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:
a) A scheme designed in accordance with the principles of the Maidstone Borough Landscape Character Assessment (Update) June 2026 b) details of the number, size, species, maturity, spacing and position of existing/proposed native trees and landscaping, in line with the Proposed Site Layout Plan (reference to be inserted) c) It shall include a detailed scheme of advance hedgerow planting proposals along the visibility splays on the eastern boundary as shown on drawing WHL-1865- 06_Rev D 240649-RAP-XX-XX-DR-TP-3200) to be implemented during the first planting season (October to March) following the commencement of development. d) Any new hedgerow planting details shall show a double staggered hedgerow with approximately 45cm spacing and consisting of 70% Hawthorn or Blackthorn, 5% Dogwood, 10% Field Maple, 10% Hazel, 2.5% Holly and 2.5% Wayfaring Tree Alder Buckthorn (10%) Hawthorn/Hazel (80 %) Sallow (10%). and shall include the siting, spacing, maturity, details of management (including should planting fail) and will follow the detailed guidance on native hedgerow planting and maintenance on our web site at Hedges - Maidstone Borough Council. The development shall be carried out in accordance with the approved details during the planting season (October to March) and completed in accordance with the approved timetable. The timetable shall include advance planting and phased planting as part of the scheme to be agreed. The approved scheme shall be fully completed no later than the first planting season following completion of the installation of the PV arrays hereby permitted.
Reason: To safeguard rural character and appearance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
24/500007/full - demolition of 5no.RESOLVED : 1. That subject to: A. The prior completion of a legal agreement in such terms as the Head of Legal Partne...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.