District Centres Regeneration update

Noted Executive 2 papers

AI summaryManchester Executive notes progress on District Centres regeneration covering Moston Lane, Gorton and Wythenshawe Civic, with over £60m of housing investment in Gorton and a development partner appointment for Moston Lane expected by March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo formal decision beyond noting the update
MoneyNo new spending consequencesFunded from existing budgets and external grants
What happens nextDevelopment partner for Moston LanePreferred bidder to be identified by March 2026
Who it affectsAll wards across ManchesterFocus on Moston Lane, Gorton and Wythenshawe Civic

What was decided

The Executive noted the contents of the District Centres Regeneration update report, which covers progress on investment, improvement and regeneration across Manchester's High Streets, Local Centres and District Centres. Report P8, P1

Why

The report provides an update on three key District Centres: Moston Lane (development partner search), Gorton District Centre (Clarion Housing Group appointed) and Wythenshawe Civic (joint venture with Muse has started early works). Report P5, P4

What happens next

A preferred development partner for the Moston Lane site is to be identified by March 2026, with a report on the outcome to come to a future Executive. Subject to planning, construction on Moston Lane could start in late 2027. Report 3.4, 3.5

Planning applications for around 70 affordable homes on the former Gorton Library site and 35 care leaver homes with Centrepoint are expected in the first half of 2026. Gorton Market refurbishment full completion is expected later in 2026. Report 3.12, 3.13, 3.10

Determination of planning applications for the first 422 affordable homes at Wythenshawe Civic is expected in late spring 2026, with demolition of the Birtles north end (C2) planned for winter 2026/27 and a Pride in Place Board to be established in summer 2026. Report 3.17, 3.19

The money

  • over £970K Shared Prosperity Fund investment in Moston Lane projects Report 3.2
  • over £60m Combined investment into Gorton from the two housing schemes Report 3.14
  • £20m Government former Levelling Up Fund (now Local Regeneration Fund) for Wythenshawe Civic Report 3.16
  • £11.9m Council contribution to Wythenshawe Civic early interventions Report 3.16
  • £25.4m Greater Manchester Good Growth Fund expected announcement in March 2026 for Wythenshawe affordable homes Report 3.18
  • £20m Ten years of Pride in Place investment for Benchill South and Wythenshawe Central Report 3.19
  • over £5m UK Shared Prosperity Fund Communities and Place funding concluded in early 2025 Report 2.11
  • £1.8m Enterprise projects delivered by Work and Skills team under SPF Report 2.11
  • over £200k Local Growth and Place Flexible Fund grant for District and Local Centres Report 2.8

Options considered

  • Chosen: Note the contents of the report. Report is an update only with no specific decisions requiring approval Report P8

Implications

  • Financial: No specific financial consequences from this report. Capital projects are governed and monitored via existing Council processes. Report P24, P26
  • Equalities: Many District Centres contain significant deprivation and health inequalities; new projects will be supported by Equalities Impact Assessments on inclusive design, housing needs and social value. Report P15, P16
  • Climate: District Centres have potential to contribute to the city's zero carbon target; fabric first design, heat pumps, solar PV, sustainable urban drainage, biodiversity and active travel will be promoted. Report P9, P10, P11, P12, P14

Who and where

  • Residents and businesses across all 17 designated District Centres and additional local centres and neighbourhoods in the programme Report 2.1, P1
  • Moston Lane community, with a new Regeneration Forum being set up with local members Report 3.6
  • Gorton residents, including future occupiers of around 70 affordable homes and 35 care leaver homes with Centrepoint Report 3.12, 3.13
  • Wythenshawe Civic area, with 422 new Social Rented homes planned and 2,000 new homes in the long-term framework Report 3.15, 3.17

Timeline

  • January 2026: Work commenced on extending Gorton Square with new features for young children Report 3.9
  • First half of 2026: Planning applications expected for former Gorton Library site and Chapman Street care leaver scheme Report 3.12, 3.13
  • March 2026: Moston Lane preferred bidder to be identified and report to come to Executive Report 3.4
  • March 2026: Greater Manchester Good Growth Fund of £25.4m expected to be announced for Wythenshawe Report 3.18
  • Late spring 2026: Determination expected on planning applications for first 422 Wythenshawe affordable homes; Gorton Square extension to complete Report 3.9, 3.17
  • Later in 2026: Full completion of Gorton Market works Report 3.10
  • 2026: Creation of a larger public square at Wythenshawe Civic; early works on culture hub, food hall and employment space Report 3.17
  • Summer 2026: Pride in Place Board to be established for Benchill South and Wythenshawe Central Report 3.19
  • Winter 2026/27: Demolition of north end of Birtles (C2) planned at Wythenshawe Report 3.17
  • 2028: Targeted completion of new housing on the Wythenshawe C2 site Report 3.17
  • Late 2027: Potential start of construction on Moston Lane, subject to planning Report 3.5

Plain English for the jargon

  • NDF (Neighbourhood Development Framework): A guide to future regeneration for a neighbourhood, adopted following public consultation, as used for Gorton
  • SRF (Strategic Regeneration Framework): A long-term vision document for a wider area, as used for Wythenshawe Civic
  • SPF (Shared Prosperity Fund): UK Government funding programme that concluded in early 2025, now superseded by the Local Growth Place Flexible grant
  • Place Management Plans: Plans outlining strategies and actions over the next 12 months to improve District Centres that do not have a development framework
  • GMCA: Greater Manchester Combined Authority, which administers devolved regeneration funding
  • MHPP: Manchester Housing Providers Partnership, which supports the Council's Affordable Housing Programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Decision The Executive note the report.
Word for word from the decision Manchester published for this meeting. Source: democracy.manchester.gov.uk

Follow this further

Built from Manchester's papers

What the report saysPro

Report to Executive

Summary

This report sets out the progress made in the investment, improvement and regeneration programme being implemented across Manchester’s designated High Streets, Local Centres and District Centres.

Significant progress has been made over the last few years with delivery of specific targeted interventions across the city designed to drive footfall, local spend, events, civic activities and maximise the economic potential of each community.

Investment has successfully delivered new public realm in Withington, Gorton and Moston Lane along with operational enhancements across a number of locations including Burnage, Chorlton, Levenshulme, Longsight and Rusholme.

The programme of regeneration continues at pace, and this report will update on recent developments in three key District Centres:

• Moston Lane, the progress made to date in the search for a development partner which is on track to conclude this spring. • Gorton District Centre, the appointment of Clarion Housing Group to deliver hundreds of new homes whilst investment continues in the public realm and upgrades to Gorton Market. • Wythenshawe Civic, the Council’s Joint Venture with Muse has commenced early works for the construction of a new culture hub, food hall and extended public square, whilst planning applications have been submitted for the first tranche of housing, to bring forward 422 new affordable homes across three sites.

Regeneration and Investment is complemented by joint working across the Council particularly between Neighbourhoods, Highways and Environmental Health / Enforcement to ensure the success of our District Centres and High Streets.

Work is ongoing with the local community to inform future plans for Newton Heath, Harpurhey and Cheetham Hill District Centres along with their relationship to the emerging regeneration funding programme, plus synergies and opportunities identified within the other Council initiatives across the city.

Recommendations

The Executive is recommended to note the contents of this report. Wards Affected: All Wards

Environmental Impact District Centres, Local Centres and High Streets Assessment - the impact of the hold the potential to contribute significantly to the issues addressed in this report on city’s zero carbon target, though the extent and achieving the zero carbon target nature of that contribution will depend on the for the city particular interventions being delivered in each centre.

Where significant new residential development is set to occur, for example, efforts will be made to reduce carbon impacts both during construction and the operational life of the new homes, with a fabric first approach to design and the selection of appropriately sustainable materials and building systems. This may include heat pumps and solar PV.

A place-based approach to District Centres promotes opportunities to develop new homes close to employment sites where appropriate and near community and leisure facilities, reducing the need to travel.

With investment and targeted physical changes many District Centres have the potential to facilitate much greater active travel than at present, and this has been a topic of focus for the development frameworks produced to date (e.g. Wythenshawe, Strangeways).

There may be options for larger interventions at a neighbourhood-wide level, be that in terms of energy generation or distribution. As these areas come forward officers will work with private developers, JV partners and stakeholders to identify and investigate such opportunities, as is being done at Wythenshawe.

Where new or improved public realm has been introduced into District Centres then shade through planting schemes, water capture through sustainable urban drainage and greater biodiversity will be promoted from the outset (e.g. Moston Lane and Withington).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix: Recent and planned works North, Central and South District CentresAppendix 712 KB Download
PDF
District Centres Regeneration updateReport 6.8 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 19 attended
BC
Councillor Bev CraigChair, apologies
RA
Councillor Rabnawaz AkbarCommittee Member, present
GB
Councillor Garry BridgesCommittee Member, present
JH
Councillor John HackingCommittee Member, present
LI
Councillor Lee-Ann IgbonCommittee Member, apologies
JM
Councillor Joanna MidgleyChair, present
TR
Councillor Tracey RawlinsCommittee Member, present
JR
Councillor Julie ReidCommittee Member, present
TF
Councillor Thomas Frederick RobinsonCommittee Member, present
GW
Councillor Gavin WhiteCommittee Member, present
AA
Councillor Ahmed AliAdvisory Member, present
SB
Councillor Shazia ButtAdvisory Member, present

All 19 on the meeting page

On this subject at Manchester

Search all
  1. District Centres Regeneration updateThis decision
  2. Update on investment in District Centres and LocalitiesNoted
  3. Minutes of the District Centres Sub GroupDecided
  4. Climate Change and District CentresNoted
  5. Findings of the District Centres SubgroupDecided
  6. Minutes of the District Centres Sub GroupDecided

More from Manchester Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Adult Social Care - Unpaid Carers Strategy 2026 – 2029Decision The Executive approve and adopt the Unpaid Carers Strategy 2026-29 Approved Open
16 Sep 2026 Housing Repairs Insourcing and Recommissioning (Part A)Decision The Executive note and agree the proposal for the Council to establish a combined insourcing and recommissio... Agreed Open
10 Jun 2026 Appointment of Executive Members and their PortfoliosDecision The Executive note the appointments of Deputy Leader and Executive Members Noted Open
10 Jun 2026 Delegation of Executive Functions to the Executive and Council OfficersDecision The Executive:- (1) Note the decision of the Leader of the Council to exercise the power under Section 9E(2)... Noted Open
10 Jun 2026 Corporate Priorities 2026/27Decision The Executive adopt the commitments made in the Manchester Labour 2026 manifesto as priorities for the Execu... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies