Resolved
135/2007 The Cabinet noted: · Spend and commitments on the approved programme since 1 April 2007 to date amounted to approximately £6.5 million; · Forecast spend during 2007/2008 as a whole amounted to £109 million; · The additions to the capital programme detailed in sections 6 of the report; · The virements approved as detailed in section 7 of the report. 136/2007 The Cabinet recommended to Council on 26 July 2007 the proposed further additions to the capital programme, outlined in section 6 of the report. 137/2007 The Cabinet recommended to Council on 26 July 2007 to adopt the changes to the Constitution as set out in Appendix 7 to the report.
Word for word from the decision Medway published for this meeting.
Source: democracy.medway.gov.uk