What the committee will consider, in order, with every paper attached to its item.
1
Procedure
Capital Programme 2010/2011 and Beyond
Decision: 193/2009 The Cabinet agreed to forward the provisional draft capital programme to Overview and Scrutiny as work in progress inviting them to offer comments on the proposals outlined. Decision page
2
Procedure
Local Air Quality Management
Decision: 195/2009 The Cabinet instructed officers to undertake a 12 week consultation period on the proposed revocation of the current Air Quality Management Areas (AQMAs) and the declaration of three new AQMAs including a large central AQMA, as set out in the report. Decision page
3
Procedure
Gateway 1 Options Appraisal: Chatham Dynamic Bus Facility
4
Procedure
Recruitment Freeze
Decision: 199/2009 The Cabinet agreed to unfreeze the following posts, as detailed in Appendix 1 to the report, to enable officers to commence the recruitment process: Business Support a) Internal Audit - Investigations Officer. b) Senior ICT Support OfficerChildren and Adults Services. c) Support Services Assistant - Elaine Centre. Decision page
5
Procedure
Outline Business Case for Strood Academy
Decision: 201/2009 The Cabinet agreed to defer consideration of the report to allow more time for detailed analysis. Decision page
Decision: 202/2009 The Cabinet accepted the tender from J. Breheny Contractors Ltd, as set out in the exempt appendix, for the phase 2 improvements to Union Street, Chatham. Decision page
8
Procedure
Chatham Dynamic Bus Facility Revised Scheme
Decision: 194/2009 The Cabinet agreed that (a) a planning application be submitted for a revised scheme (as described in this report, and as shown in the sketches appended to it). (b) the loss of existing public open space in the proposed site be advertised in the local press in accordance with s123 (2A) of the Local Government Act 1972 and the Director of Regeneration, Community and Culture be delegated authority, in consultation with the Portfolio Holder for Community Services, to consider any... Decision page
9
Procedure
Capital Budget Monitoring
10
Procedure
Gateway 3 Contract Award: Kent Buying Consortium Print Services
Decision: 203/2009 The Cabinet approved the inclusion of the 23 companies, set out below, who submitted the most economically advantageous tenders, on a select list for the provision of print services, at prices to be agreed at the time of order when calling off from the framework: Lot 1 - Document printing: A R Adams & Sons. Belmont Press. Cliffe Enterprise. Corporate Document Services Ltd. County Print & Design. DA printers. Delga Group. Grammer & Co. Headley Bros (Holdings) Ltd. Liberty Printers (AR &... Decision page
11
Procedure
Revenue Budget 2010/2011
Decision: 192/2009 The Cabinet agreed to forward the provisional draft budget to the Overview and Scrutiny Committees as work in progress inviting them to offer comments on the proposals outlined. Decision page
12
Procedure
Second Quarter Performance Report 2009/2010
13
Procedure
Local Development Framework: Revised Local Development Scheme
Decision: 196/2009 The Cabinet agreed that the revised Local Development Scheme, appended to the report, be submitted for approval by the Secretary of State for Communities and Local Government subject to the Director of Regeneration, Community and Culture, in consultation with the Portfolio Holder for Strategic Development and Economic Growth, being delegated authority to make minor revisions to the scheme in conjunction with the Government Office for the South East. 197/2009 The Cabinet agreed that the... Decision page
14
Procedure
Revenue Budget Monitoring
15
Procedure
Gateway 3 Contract Award: Mental Health Floating Support Service
Decision: 204/2009 The Cabinet agreed that the contract for the Supporting People Mental Health Floating Support Service be awarded to In Touch on the bases of the outcome of the procurement process for a period of 3 years with the provision to extend for a further 1 year thereafter. Decision page
16
Procedure
Historic Building Grant Scheme Rochester and Chatham
Decision: 198/2009 The Cabinet agreed to confirm its support in principle for applying for an English Heritage grant under the Decision page
Last time, and what carried over
The committee last met on 3 November 2009. None of its items return this time. Point at any item to follow a thread. Procedural items are left out.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
What should we tell you?
Medway, Cabinet
Cabinet: 3 kinds of updateMedway, sent the same day
PDF
Papers publishedCapital Programme 2010/2011 and Beyond
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 24 NovemberThe committee's resolutions, the day they are recorded
ABC
Your words found in the papersEvery match, with the page it is on
Each update links to the paper and the council's own copy
// POST to your endpoint, signed, the moment it happens
{
"event": "papers.published",
"council": "medway",
"committee": "Cabinet",
"meeting": "2009-11-24",
"papers": 0,
"items": 16,
"source": "democracy.medway.gov.uk"
}
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.
PlanProPrice£99 per user a monthStartsToday, full access straight away
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.