What the committee will consider, in order, with every paper attached to its item. Amherst Hill Design Brief is the main business.
Decision: 79/2010 The Cabinet noted the revenue and capital outturns as reported in sections 4, 5, 6 and 7 of the report and approved the actions taken in producing the Statement of Accounts as set out in these sections. 80/2010 The Cabinet recommended to the Audit Committee that it approves the draft Statement of Accounts for 2009/2010. Reasons: There is a statutory requirement to approve the Statement of Accounts prior to 30 June 2010. Decision page
Decision: 81/2010 The Cabinet noted the content of the report and recommended it to the Audit Committee, in accordance with the CIPFA Code of Practice. Reasons: In line with CIPFA’s Code of Treasury Management Practice an annual report must be taken to Cabinet detailing the Council’s treasury management outturn within six months of the close of each financial year. Decision page
Decision: 82/2010 The Cabinet agreed that the current Air Quality Management Areas be revoked and the three new Air Quality Management Areas be declared as follows: Central Medway High Street, Rainham Pier Road, Gillingham. Reasons: The Council has a duty to designate Air Quality Management Areas where the Air Quality Objectives are unlikely to be met. Decision page
Decision: 83/2010 The Cabinet approved statutory consultation on the draft Amherst Hill Design Brief commencing in mid-July 2010 for 6 weeks. Reasons: To allow progress towards adoption of the brief as a Supplementary Planning Document (SPD) and to ensure that the site is developed in a manner that minimises the visual impact on Fort Amherst and the local area. Decision page
Decision: 84/2010 The Cabinet a uthorised officers to proceed with an initial informal consultation period to allow views to be expressed on the proposal to make a prescribed alteration to Rivermead School from a Hospital School to a Community Special School catering for statemented SEN children with complex needs aged 11-19 on 1 September 2011. Reasons: To minimise the following risks: a risk to the future viability of Rivermead school if redesignation does not take place a risk that it could undermine... Decision page
Decision: The Cabinet noted the performance for 2009/2010. Reasons: Full and accurate performance reporting to elected Members is consistent with best practice, and will allow Members to review the Council’s performance. Decision page
Decision: 85/2010 The Cabinet agreed to unfreeze the following posts, as detailed in Appendix 1 to the report, to enable officers to commence the recruitment process: Regeneration, Community and Culture a) Head of Safer Communities b) Head of Waste Services Business Support c) Service Support Assistant d) Benefit Development Officer. Reasons: The posts presented to Cabinet support the efficient running of the Council. Decision page
Decision: 86/2010 The Cabinet agreed to continue the 2010/2011 Capital works under its existing contract with Mears, on the basis of the discount on their existing contract rates. 87/2010 The Cabinet agreed that the Monitoring Officer may grant a waiver to Contract Rules to continue with the existing consultant project team on their existing tendered rates. 88/2010 The Cabinet delegated authority to the Assistant Director, Housing and Corporate Services, in consultation with the Portfolio Holders for... Decision page
Decision: 89/2010 The Cabinet agreed to delegate authority to the Chief Finance Officer, in consultation with the Portfolio Holder for Finance, to finalise the response on the prospectus on HRA self financing, to be submitted to CLG by 6 July 2010. 90/2010 The Cabinet agreed that this decision is considered urgent and therefore should not be subject to call-in. Reasons: That the consultation response in appendix 2 to the report be submitted to CLG to ensure that Medway Council’s views are taken into... Decision page
Decision: 91/2010 The Cabinet recommended to Full Council to: (i) agree the proposals set out in this report and its appendices to redress the budget shortfall (ii) approve the use of reserves accruing from the underspend in 2009/10 to fund any necessary one-off costs in implementing the changes. 92/2010 The Cabinet authorised the Directors and Chief Executive to consider and determine all consultation responses received in respect of their Directorates. 93/2010 The Cabinet agreed that decision no.... Decision page
Item 52 is where most of this meeting's papers sit: 2 papers, about 11 MB.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 13 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 8 June 2010. 6 of its items lead into this meeting; 8 items are new. Point at any item to follow a thread. Procedural items are left out.
Petitions and E-Petitions, Cabinet Advisory Groups, Gateway 1 Options Appraisal: Connexions Services Provision, Gateway 1 Options Appraisal: Mercury Abatement and Improvements to Medway Crematorium do not return this time.
See the 8 June meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Medway, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies