72/2010 The Cabinet agreed to the preferred option (1) in the report, open market procurement for the tree maintenance contract from 1 July 2011. Reasons: By commencing procurement of the tree maintenance contract now, service continuity can be adequately planned and financial award decisions made through the 2011 budget setting process.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks agreement to start the procurement of a new tree maintenance contract, to commence from July 2011 for a period of 5 years plus an extension, subject to performance and market suitability, for a period (or periods) of up to 2 years.
1. Budget and Policy Framework
1.1The tree maintenance contract will enable the Council to meet its duty of care obligations in respect of tree management and will facilitate the completion of tree work to deal with legitimate customer requests for service and complaints.
1.2To ensure business continuity from expiry of the existing contract (July 2011) authority is requested to commence the procurement of a new contract for a period of 5 years plus an extension, subject to performance and market suitability, for a period (or periods) of up to 2 years. The decision falls within the policy and budget framework. How the contract will address some of the council’s strategic objectives is set out in section 4.2.
2. Related Decisions
2.1Officer Scrutiny Panel approved an extension to the existing contract on 6 January 2010 to enable this contract to follow the same procurement timetable as the playground maintenance contract and to ensure alignment with the council’s budget setting process. 3. Background
3.1The current tree maintenance contract was awarded to Blenwood Limited in April 2006. The contract was let as a three-year contract from 1 July 2006 with an option to extend subject to satisfactory performance for a further 24 months to 1 July 2011.
3.2The contract covers safety related work to deal with dead trees or branches, obstructions to roads, other tree hazards and an emergency response service. The contract also facilitates the completion of tree work to deal with legitimate customer requests for service and complaints. Some works such as the twice yearly pruning of trees to remove low branches and the provision of an emergency response service are undertaken on a planned basis and some following works orders placed by the Authorised Officer.
3.3The existing contract is managed through a combination of ad-hoc performance checks, joint site visits and contract review meetings that are scheduled on a monthly cycle. There have been no significant cost or volume variances to the existing contract since it was tendered and the main benefits of the contract (to ensure Medway Council’s trees are pruned to a high standard and in a cost effective way) have been achieved.
3.4A host service arrangement has been investigated and discounted as there are no opportunities for a joint procurement exercise or shared tree maintenance service in Kent at this time. An in-house option has also been discounted on the basis of on costs around salaries and service continuity.
3.5Following an options appraisal, this report highlights a preferred option of external contractor supply because there is an established, but small market of specialist suppliers.
4. Business Case
4.1Business Case Summary
4.1.1 The tree maintenance contract enables the Council to fulfil its statutory duty of care obligations relating to tree management and facilitates the completion of tree work to deal with legitimate customer requests for service and complaints in line with the council’s adopted tree policy.
4.2Strategic Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.