82/2010 The Cabinet agreed that the current Air Quality Management Areas be revoked and the three new Air Quality Management Areas be declared as follows: Central Medway High Street, Rainham Pier Road, Gillingham. Reasons: The Council has a duty to designate Air Quality Management Areas where the Air Quality Objectives are unlikely to be met.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
To inform Cabinet of the outcome of the detailed assessment of air quality in Medway produced in August 2009 and the outcome of the 12-week statutory consultation which ended on 26 March 2010 on the declaration of three Air Quality Management Areas (including the revocation of the existing six AQMAs).
1. Budget and Policy Framework
1.1The recommendations of this report are within council’s policy and budget framework. The Council’s Constitution (part 1 – responsibility for local choice functions, as set out in chapter 3 – responsibility for functions), assigns the responsibility for the discharge of any function relating to part IV of the Environment Act 1995 to Cabinet.
1.2Air Quality Management links to the current Local Transport Plan - improving air quality is one of the four National shared high level priorities for transport. As part of the development of the third Local Transport Plan (LTP3) the National Environment priority (Priority 2) includes reference to improving air quality. Cabinet approved the draft LTP3 on 20 April 2010 for public consultation this summer. Following consultation approval will be sought for acceptance of the final plan in early 2011.
1.3The topic also links to the Clean and Green priority set out in the Council Plan. The cost of air quality monitoring and the review and assessment process will be met from existing budgetary provision. 2. Background
2.1Part IV of the Environment Act 1995 places a statutory duty on local authorities to review and assess the air quality within their area and take account of Government guidance when undertaking such work.
2.2The National Air Quality Strategy contains standards and objectives for the following eight key air pollutants, which have been demonstrated to have adverse effects on human health: -
2.3The locations where the objectives apply typically include residential properties and schools/care homes for annual mean pollutant objectives and high streets for short-term pollutant objectives.
2.4In areas where air quality objectives are not likely to be met by the relevant target date, local authorities are required to declare an Air Quality Management Area (AQMA) and develop an action plan in pursuit of the air quality objectives. The objective for ozone is excluded from this regime as it is not a locally derived pollutant.
2.5How do we measure air pollution? Medway has a network of 25 nitrogen dioxide diffusion tube sites and three continuous air quality monitoring stations which provide us with an indication of nitrogen dioxide levels in these areas. The three continuous air quality monitoring sites are designated as an urban roadside site which is located at Chatham Girls Grammar School, an urban background site which is located at Luton Junior School and a rural background site which is located at Stoke Primary School. Total coverage of the Medway area is not feasible so diffusion tube monitoring is undertaken at locations which have been identified as potential hot spots.
Dispersion modelling is also used when hot spot locations have been identified and a more detailed assessment is needed. This computer modelling uses data on topography, meteorology, traffic composition, vehicle speeds and the locations of sensitive receptors to predict pollutant concentrations.
2.6Medway’s air pollution The objectives for six out of the seven relevant pollutants are being met across Medway. However, concentrations of nitrogen dioxide have been confirmed to exceed the 2005 annual mean objective value of 40 µg/m3 at several locations across Medway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.