Resolved

86/2010 The Cabinet agreed to continue the 2010/2011 Capital works under its existing contract with Mears, on the basis of the discount on their existing contract rates. 87/2010 The Cabinet agreed that the Monitoring Officer may grant a waiver to Contract Rules to continue with the existing consultant project team on their existing tendered rates. 88/2010 The Cabinet delegated authority to the Assistant Director, Housing and Corporate Services, in consultation with the Portfolio Holders for Finance and Housing and Community Services, to agree a further discount with Mears for ongoing capital works that may be required following the completion of the Asset Strategy and subsequent capital programme of works. Reasons: · To ensure Decent Homes target is achieved by the December 2010 deadline. · To maintain continuity of works and maximise value for money using the existing tendered contract. · To continue to build the trust and confidence of tenants now that the decent homes programme has recommenced. · To retain a high performing principal Contractor and project team. · To mitigate risk issues in relation to the existing Mears Contract.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

To seek approval to the completion of the Decent Homes Programme 2010/2011.

1. BUDGET AND POLICY FRAMEWORK

1.1The decision is within the Council’s policy and budgetary framework.

2. RELATED DECISIONS

2.1The Cabinet report dated 4 August 2009 and decision outlining the tendering proposals and Procurement Board report dated 23 September 2009.

3. BACKGROUND / INTRODUCTION

3.1The Assistant Director (Housing and Corporate Services) advised Members in December 2008 that due to the problems the Council had experienced with Erinaceous and 3Cs, the Council’s previous contractor, the Capital Works element of the HRA Housing Contract would be re-tendered.

3.2Consultants were appointed to help drive the Decent Homes Capital Programme and to ensure that the programme was delivered and achieved on target for the end of the financial year 2009/2010. This has proved successful, and a Gateway 4 contract management report will be presented in the near future. 3.3 Delegated authority was granted to the Assistant Director (Housing and Corporate Services) by Cabinet on 4 August 2009 to award the contract subject to consideration by Procurement Board.

3.4Tenders were invited and contract awards made for Decent Homes Building capital works and Heating Installations for 09-10 following both Cabinet and Procurement Board approvals. The council awarded works to both United House Limited and Mears.

3.5Performance monitoring of both contractors has been ongoing in relation to works awarded to both Mears and UHL a summary of project managers KPI details is shown in the table below:

Decent Homes Contractors Performance Monitoring – Summary table

Overall Project Percentage Progress in Making Good Quality of Workmanship

Contractor Performance Collaborative Approach Financial Management

Customer Satisfaction Contractor Design (If

Total Project Score Time Management

Health and Safety

Sub-contractors Management of

Applicable) Defects Project Contr

As at 02/05/10 MEARS 4 4 5 4 4 4 4 4 4 5 42 84% UHL 4 4 4 2 3 4 4 3 4 3 35 70%

3.6Re tendering of the decent homes works is unlikely to result in improved value for money, will waste considerable time and ultimately lead to a failure to meet the 2010/2011 decent homes target. The proposed continuity with the existing Mears Contract will ensure that the 2010/2011 decent homes target is achieved, continuity and good contract performance standards are maintained, continue to build tenant trust and confidence and demonstrate VFM.

3.7The Monitoring Officer has been requested to agree an exemption to contract rules in order to extend the contracts of the existing consultant project team. The total fee for each specialist consultant service will not exceed the EU threshold for service contracts. Services covered include Project Management, Quantity Surveying, Clerk of Works, Mechanical and Electrical Services and CDM coordinator. 3.8 Following completion of a full stock condition survey, a Housing Asset Strategy is in the process of being developed and this will provide options and identify the resources required to improve and maintain the stock. Options regarding future capital works programmes following the completion of the Asset Strategy will be brought before Members in the future, for consideration.

4. SUMMARY OF THE BUSINESS CASE

4.1Strategic Context

4.1.1 The Council is required to ensure that 100% of its housing stock meets decent homes standards (set by government) by December 2010. Awarding the 2010-11 Decent Homes works as recommended below will ensure that this target is achieved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Completion of Decent Homes Programme 2010/2011Report 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, apologies
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, apologies
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Rose CollinsonOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: Completion of Decent Homes Programme 2010/2011This decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open