Woodlands School Extension

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 28 September 2010. Below is the council's own wording, with the papers it was decided on.

Item102

Resolved

141/2010 The Cabinet agreed Option D, as set out in the report, and that the Section 106 Contribution for Grange Farm be used to fund this work. 142/2010 The Cabinet agreed the proposed project approval process outlined in the addendum report. 143/2010 The Cabinet asked the Audit Committee to consider the control issues arising from this report noting that Cabinet has agreed the proposed project approval process outlined in the addendum report. Reasons: To ensure that procedures are in place to protect the Council from any financial mismanagement and to ensure that it obtains value for money in all circumstances. To ensure that Woodlands Primary School can continue to operate as a 2 form of entry (FE) school, at the lowest possible cost to the Council.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report identifies potential procurement and other issues that have arisen from works carried out at Woodlands Primary School, Gillingham, and to identify further work needed together with the budgetary provision to carry it out.

1. Budget and Policy Framework

1.1Option D is a matter for Cabinet to decide, however, the additional money needed to carry out the extra works to Woodlands School (options A, B and C) is not within the existing budget and will have to be agreed by Full Council.

1.2This report will also be received by the Audit Committee on 28 September 2010, who will be asked to consider the report and any further control measures necessary.

1.3The Cabinet is asked to accept this as an urgent matter to enable the required works to be carried out.

Background

2.1Woodlands School, Gillingham was a 1 form entry (1FE) primary school. In 2006 it had 200 pupils on the role and had received an “outstanding” ofsted inspection.

2.2Officers appear to have agreed with the School towards the end of 2007 that the school facilities should be expanded to facilitate two forms of entry, in order to increase the number of primary school places available in the Gillingham area. At the time, this was consistent with Medway School Organisation Principles that said that popular and successful schools should be able to expand. Woodlands Primary School was at that time consistently oversubscribed.

2.3On 22 April 2008, Cabinet (decision 106/2008) agreed the arrangements for admission in 2009 for community and voluntary controlled primary schools. The arrangements included a change in admission arrangements for Woodlands Primary School with an expansion from a planned admission number of 45 pupils per year group to 60 pupils per year group, to make it a 2FE school in line with the then current pupil projections.

3. Work to Woodlands School

3.1Work would have been necessary at Woodlands School, as the increased intake necessitated adaptation to the size and composition of the school facilities needed to change. However, internal audit have been unable to find evidence as to whether any formal proposal of how the school could be extended to accommodate the increased pupil numbers was prepared, either by the Council’s Learning and Achievement Division or by the School.

3.2Minutes of the meeting of the Children’s Services Capital Group on 18 January 2008, chaired by the Assistant Director, Learning & Achievement, include, in the ‘A.O.B.’ section, “Woodlands Primary: This needs to be added into the programme for 2008/09. The cost will be £750,000 from developer contributions to increase the school to 2FE.” This appears to represent the only written record of any decision, and as set out in 3.1 above, there is no record or specification of what the £750,000 represents.

3.3The estimated cost of £750,000 appears to have been arrived at in advance of any detailed planning, and the Learning and Achievement Division appears to have taken note of the schools view from the school that the work could be completed within that figure. However, the then Head of Design and Surveying had been consulted and had advised that the cost appeared low in view of the works required, but conceded that the school could probably achieve savings through using cheaper contractors. Some plans were apparently drawn up at this stage, but no evidence of these has been located.

3.4Therefore we are unable to be clear as to what was the original specification for the work that was required to Woodlands School and whether the work was necessary and proportionate to achieve a 2FE school.

4. Authorisation for budget allocation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Woodlands School Extension: Addendum ReportAddendum 7 pages Download
PDF
Woodlands School ExtensionReport 126 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
RC
Councillor Rodney Chambers (Con)Committee Member, apologies
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, apologies
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, apologies
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Rose CollinsonOfficer, in attendance

All 17 on the meeting page

On this subject at Medway

Search all
  1. Woodlands School ExtensionThis decision
  2. Gateway 4 Procurement Post Project Completion Review: Woodlands School - Improvements to Nursery, Reception and SEN ProvisionNoted
  3. Gateway 3 Contract Award: Woodlands School - Improvements to Nursery, School Reception and SEN ProvisionApproved

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies