The Cabinet noted the spending and funding forecasts summarised at tables 1 and 3 in the report. The Cabinet noted the additions to the Capital Programme and virements as detailed in paragraph 5.1 of the report. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1At its meeting on the 25 February 2010, the Council approved a capital programme for 2010/2011 and future years of some £116m. Subsequent funding announcements have increased the programme to nearly £124 million. Details of the changes to each directorate capital programme are explained in individual commentaries in Section 4 of this report.
2.2This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
2.3Medway Council has a capital programme for 2010/2011 now in excess of 200 individual schemes. Approximately 140 of these are principal schemes, i.e. over £100,000, including a significant number rolled forward from earlier years, and the substantial regeneration programme being progressed by Medway Renaissance.
2.4A report was presented to Full Council on 29 July detailing the impact of the Government’s public spending reductions on the Council’s capital programme in this financial year. Council agreed a number of measures to compensate for a loss of £908,500 funding against the approved Local Transport Plan (LTP) programme and a loss of £1,006,775 of expected Public Service Agreement (PSA) reward grant. These are discussed in more detail in Section 4 of this report.
3. Progress
3.1Table 1 below summarises the current overall expenditure and forecasts on capital schemes within each directorate for the 2010/2011 capital programme. This table summarises Appendix 1. Appendices 2 to 6 show the position by directorate.
Table 1: Spend to Date
forecast to spend Commitments to Forecast spend
Variance (is an
in later years underspend) Programme
programme Spend and 2010/2011 Approved
Approved date Directorate
£’000 £’000 £’000 £’000 £’000 Business 15,308 11,682 5,444 5 3,631 Support Dept Children & 50,498 30,053 2,877 (215) 20,229 Adults Regeneration, Community & 55,529 49,114 20,247 9 6,423 Culture Members 2,468 2,366 287 (2) 100 Priorities TOTAL 123,803 93,215 28,854 (203) 30,383
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
☺ Scheme progressing on time and within budget
Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices: Table 2: Project Progress Summary
TOTAL Progress Monitoring ☺ SCHEMES
Business Support 23 1 1 25
Children & Adults 71 15 0 86
Regeneration, Community & Culture 61 7 2 70
Members Priorities 26 6 0 32
TOTAL 181 29 3 213 36 2 4. Specific Scheme Monitoring Issues and Completions 85% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
The majority of the capital programme is a continuation of funding previously agreed, with the following changes and additions:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.