Cabinet noted this item on Tuesday 14 February 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet noted the findings outlined in this report .
CABINET
14 FEBRUARY 2012 GATEWAY 4 PROCUREMENT POST PROJECT COMPLETION REVIEW: WOODLANDS SCHOOL - IMPROVEMENTS TO NURSERY, RECEPTION AND SEN PROVISION Portfolio Holder: Councillor Les Wicks, Children’s Services
Report from: Rose Collinson, Director of Children and Adults
Author: Cathy Arnold, Capital Programme Manager
Summary This report presents Cabinet with a post project review/appraisal of a high risk contract completed at Woodlands School to deliver improvements to the nursery, reception and SEN provision as highlighted within 2.1.2 of this report.
This follows the award of contract following a Gateway 3 report to Cabinet on 21 December 2010 (decision number 225/2010).
The approved Procurement Gateway 3 Report relating to this Gateway 4 report is available upon request.
This Procurement Gateway 4 report has been approved for submission to the Cabinet after review and discussion at Children’s and Adult’s Directorate Management Team and Strategic Procurement Board.
1. Budget and Policy Framework
1.1Post Project Appraisal / Contract Management
This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework as highlighted within the Procurement Gateway 3 Report on 21 December 2010.
1.2Funding/Engagement From External Sources
Not applicable to this procurement. 2. Background
2.1Contract Details
2.1.1 This contract is a Works/Construction contract
2.1.2 Supplier Details
This Gateway 4 Report relates to the contract awarded to B W May & Sons Limited for construction works at Woodlands School. The works provided:
reconfigured and additional nursery space alongside the day nursery to allow for 35 children to attend from 3 years and improve transition for children from nursery to reception, with provision for children from birth to reception age additional classroom accommodation to allow for PAN increase from 45 to 60 in each year group, providing capacity for an additional 105 pupils overall dedicated SEN area for 10 children in addition to school roll, meaning these children no longer have to be educated out of area nurture room for children with emotional needs new family room with storage and 1-1 room alongside enabling a full range of courses and activities to be offered to families ranging from nutrition classes, teenage cookery courses, to family support sessions and breakfast clubs training room for the SureStart Centre to enable staff training and courses for the community to be delivered new access control and fire alarm system works to bring all aspects of the building into line with current construction legislation.
2.1.3 Contract Description
The contract was completed between January and August 2011 to provide improvements to nursery, reception and SEN provision at Woodlands School. The form of contract used was JCT Design & Build Contract (2005 Edition, 2009 Update).
2.2Permissions Required
This report provides the Cabinet with a post project appraisal and concludes this contract at the end of the contract duration of 8 months on the basis that this contract was for a one-off procurement requirement and because the contract has fulfilled requirements in accordance with the service specification and associated contract terms and conditions. The works described in the contract documents on drawings and in specifications have all been completed as required to the time, quality and cost parameters set out in the contract.
3. Options This was a one-off construction contract and the works have been completed in accordance with the contract terms.
4 Procurement Project Outputs / Outcomes
The procurement outcomes/outputs identified as important at Gateway 1 to the delivery of this procurement requirement and identified as justification for awarding the contract at Gateway 3, have been appraised in the table at the end of section 4 of this report, to demonstrate how the procurement contract and corresponding supplier has delivered these outcomes/outputs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gateway 4 Procurement Post Project Completion Review: Woodlands School: Improvements to Nursery, Reception and SEN ProvisionReport | 34 KB | DownloadRead as text |
Follow Cabinet at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... | Approved | Open |
| 22 Sep 2026 | Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... | Approved | Open |
| 22 Sep 2026 | Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... | Noted | Open |
| 22 Sep 2026 | Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... | Noted | Open |
| 22 Sep 2026 | Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.