Gateway 1 Options Appraisal: Sir Joseph Williamson's Mathematical School New Design/Technology Building

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 30 November 2010. Below is the council's own wording, with the papers it was decided on.

Item149

Resolved

211/2010 The Cabinet agreed that tenders are invited from approved contractors on the KCC select list for the construction of the new facilities for English, Design Technology, Art and Science at Sir Joseph Williamson’s Mathematical School, under a single stage tender using a standard Joint Contracts Tribunal (JCT) form of contract. Reasons: The new facilities are required to enable the school to deliver the quality of curriculum offer for the key subjects as described in the business case section of the report and the capital programme approved by Cabinet in February 2010 included funding for the project.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to commence the procurement process, to invite tenders for the Sir Joseph Williamson’s Mathematical School new design/technology building scheme from contractors selected from the Medway Council approved framework.

1. BUDGET AND POLICY FRAMEWORK

1.1The project is within the policy and budgetary framework, being consistent with the provisions outlined in the council’s 14-19 strategy. The removal of the temporary buildings is in support of Medway’s policy of replacement of temporary accommodation with permanent buildings and supports our planning principles.

2. RELATED DECISIONS

2.1Departmental Management Team confirmed approval of the business case Gateway 0 paper, to proceed with detailed design on the new Design Technology/Art building option on 13 May 2010.

Background

3.1Following the above approval from Departmental Management Team on 13 May 2010, a design team has been established to develop the project to RIBA (Royal Institute of British Architects) stage G. This includes the relevant survey works to ensure any risks are managed or mitigated and detailed cost planning has been undertaken. The design is now sufficiently developed to approach construction companies to provide tendered costs. This report seeks approval to proceed to Gateway 2 to invite tenders for the scheme from contractors selected from, Kent County Council’s select list of approved contractors.

4. BUSINESS CASE

4.1Business Case Summary

4.1.1 The project is to provide better quality accommodation for English, Science, DT and Art, which will be sized as per the DfE guidance - building bulletin 99. This will replace a number of undersized classrooms by 12: this being seven general classrooms and five DT rooms. This will allow improved delivery of the curriculum.

4.1.2 The scheme will relocate the current DT and Art classrooms in the new building together with new accommodation for Design Technology comprising Manufacturing Product and Design and practical Food preparation facilities. This will allow relocation of the English department in the space vacated. The improved accommodation in the main building will allow the temporary buildings to be demolished. This gives better adjacencies for English with the Music Department and allows sufficient space for Drama. The space vacated by Drama, currently in the Science area, will allow for expansion of the science department in the future, where again the rooms are undersized.

4.2Strategic Context

4.2.1 The project will support the council’s 14-19 strategy in offering 21st century accommodation for Art and Design Technology in dedicated Manufacturing and Product Design and Food preparation facilities. This proposal will complement the new high quality facilities available at Mid Kent College and other local secondary schools. The school aspires to lead the way in the regeneration of manufacturing in Medway through its support for an outstanding 14 –19 Manufacturing Product and Design curriculum. The school has an active programme of support to students from other local schools in this curriculum area and the development of this accommodation will significantly enhance the vocational learning experience available to local students of all ages.

4.2.2 In support of Medway’s SEN strategy, the school is a designated school for children with physical disabilities. The new buildings will be DDA compliant (Disability Discrimination Act) allowing improved access for these pupils.

4.2.3 The removal of the temporary buildings is in support of Medway’s policy of replacement of temporary accommodation with permanent buildings and supports our planning principles.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Options Appraisal: Sir Joseph Williamson's Mathematical School New Design/Technology BuildingReport 265 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, apologies
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, apologies
RC
Robin CooperOfficer, in attendance
MH
Mick HaywardOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 1 Options Appraisal: Sir Joseph Williamson's Mathematical School New Design/Technology BuildingThis decision
  2. Project Commencement/Options Appraisal - Gateway 1 Report: Advocacy Service for Parents with Children in or on the Edge of CareAgreed
  3. Gateway 1 Project Commencement/Options Appraisal: Provision of Residential and Nursing Care for Older People (Aged 65+)Agreed
  4. Gateway 1 Project Commencement/Options Appraisal: Recycling Resource Management (RRM) procurementAgreed
  5. Gateway 1 Project Commencement/Options Appraisal - Medway TestNoted
  6. Gateway 1 / Gateway 3: Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund WorksAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies