Gateway 3 Contract Award: Quality Public Transport Corridors Road Improvement Works - North Dane Way Improvement Scheme

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 30 November 2010. Below is the council's own wording, with the papers it was decided on.

Item152

Resolved

214/2010 The Cabinet agreed that the contractor Interserve be engaged for works in relation to Quality Public Transport Corridors improvement works as follows: North Dane Way bus priority measures provided their price is within the budget envelope of £800,000. Reasons: This procurement process is part of a wider strategy to improve the reliability, quality and attractiveness of public transport across Medway. For works to be completed by 31 March 2011, and for funding to be retained, it was imperative be considered by Cabinet on 30 November 2010.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report details the reasons for the engagement of the recommended contractor, Interserve for the completion of works for the North Dane Way Quality Public Transport Corridor QPTC improvement scheme. The preferred contractor has been procured through the Highways Agency East and South East Asset Management Framework.

1. Budget and Policy Framework

1.1All the schemes and elements of the QPTC Project accord with Medway’s Local Transport Plan (2006-11) and the Project is funded from the Government’s Community Infrastructure Fund (CIF). The project has been designated high risk and is therefore a matter for Cabinet.

2. DECISION ISSUES

2.1This report uses the same approach that has been applied for the procurement of the Rochester, Corporation Street and Strood Riverside schemes which started on-site on Monday 8 November and because we now have a relationship with the contractor who we have been working very closely with during the past 6 weeks.

2.2In procuring this scheme it is hoped that savings can be made because of the Contractor’s involvement in the schemes described above. Officer time will also be saved and there would of course be opportunities to move staff between sites if required to overcome any resource or technical pressures. The estimated scheme cost is £800,000 and is within the QPTC budget. 2.3 For works to be completed by 31 March 2011, and for funding, therefore to be retained, it is imperative that this report be presented to Cabinet on 30 November 2010.

2.4This procurement is being conducted using the Highways Agency East and South East Asset Management Framework. Interserve has been chosen as the recommended contractor on the basis of a schedule of rates originally tendered for the framework contract. 16 Sample Schemes were priced for the framework (see 2.3 Exempt Appendix), 4 of which (SS4, 4a, 5 and 13) were considered accurately reflective in total of the elements contained within the two schemes relating to this report. Under the framework protocols the appointed contractor must provide at least 2 quotes for sub-contracting work and materials. All accounting on this framework is open book.

2.5The processes used in this procurement fully comply with the Framework protocols. All evaluation has been scrutinised and passed by the Highways Agency East and South East Asset Management Framework Board.

2.6As an exact tender price is not currently available, it is asked that Cabinet accept this report on the basis that the submission will not exceed the £800,000 budgeted for these two schemes, and that Interserve clearly offers the best price based on a schedule of rates derived from the original framework tender.

2.7Although it is unlikely that prices have varied, it must be acknowledged that it is possible that prices may have dropped from those originally tendered for the framework contract, and therefore from the schedule of rates used in this case. It is felt that time constraints restrict the procurement route to that of a direct appointment only, and that any savings made by holding a mini competition will be vastly outweighed by the risk of losing funding. It is possible, as part of the chosen process for the Council to refine the design in order to ensure that the scheme is affordable.

3. RELATED DECISIONS

3.1A Gateway 3 report seeking the use of the Highways Agency East and South East Asset Management Framework for the procurement of the Rochester, Corporation Street and Strood Riverside schemes was passed by Procurement Board on 18 August 2010 and by Cabinet on 7 September 2010.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Quality Public Transport Corridors Road Improvement Works: North Dane Way Improvement SchemeReport 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, apologies
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, apologies
RC
Robin CooperOfficer, in attendance
MH
Mick HaywardOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: Quality Public Transport Corridors Road Improvement Works - North Dane Way Improvement SchemeThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies