The Cabinet noted: (a) The spending forecasts summarised at Tables 1 of the report; (b) The budget virements and additions as detailed in paragraphs 4.2.2, 4.2.3 and 4.3.1 of the report. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2012/13 and future years amounts to £110.6million, comprising £83.0million in respect of brought forward schemes and £27.6million of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendices. The accompanying narrative provides a brief description of each scheme, describing the progress of each and the outputs achieved. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate, with narrative from the project managers providing a more detailed explanation of the progress of each scheme against its plan.
Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2012 Approved
Spend to
Forecast Variance 2012-13 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,138 26,886 3,192 4,060 0 Department Children and 162,583 90,280 51,888 20,325 (90) Adult Services Regeneration, Community and 93,482 63,479 18,075 11,249 (679) Culture Member Priorities 1,993 996 515 460 (22) TOTAL 292,195 181,642 73,670 36,094 (790)
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 11 1 0 12 Children & Adults 45 29 0 74 RCC 45 5 1 51 Member Priorities 23 1 0 24 Total 124 36 1 161 4. Specific Scheme Monitoring Issues and Completions 77% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
4.1.1 There have been no changes to the approved programme since the previous report and no schemes are predicting a variance to budget.
4.1.2 However, the scheme in respect of demolition of the Civic Centre was underpinned by anticipated funding of £250,000 from rental income. This will not now be forthcoming and alternative means of funding are being explored.
4.2Children and Adults
4.2.1 The 2012-13 capital budget reported to Cabinet on 30 October 2012 was £72.0 million, comprising rolled-forward budget of £63.8 million, together with new approvals amounting to £8.1 million.
4.2.2 Since Quarter 2 £325,000 has been added to the condition programme, increasing the directorate’s total capital programme to £72.3 million. This represents the extent to which school contributions have supplemented the funds available to undertake schools condition works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.