Resolved
a) The Committee noted the spending forecasts summarised at Table 1 of the report; and b) The Committee noted the budget virements and additions to the capital programme as detailed in paragraphs 4.1.1, 4.2.1, 4.3.1 and 4.4.1 of the report.
Business Support Overview and Scrutiny Committee noted this item on Wednesday 19 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
a) The Committee noted the spending forecasts summarised at Table 1 of the report; and b) The Committee noted the budget virements and additions to the capital programme as detailed in paragraphs 4.1.1, 4.2.1, 4.3.1 and 4.4.1 of the report.
2.1The approved capital programme for 2013/14 and future years is £98.5m, being £41.6m in respect of brought forward schemes and £56.8m in respect of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendices. The accompanying narrative provides a brief description of each scheme, describing the progress of each and the outputs achieved. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate, with narrative from the project managers providing a more detailed explanation of the progress of each scheme against its plan. Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2013 Approved
Spend to
Forecast Variance 2013-14 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,195 28,529 2,820 2,776 (70) Department Children and 164,099 122,302 22,276 19,604 84 Adult Services Regeneration, Community and 103,287 52,914 25,541 24,832 0 Culture Member Priorities 1,333 707 395 216 (15) TOTAL 302,914 204,452 51,033 47,427 (3)
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 6 5 0 11 Children & Adults 36 17 0 53 RCC 45 8 0 53 Member Priorities 18 3 0 21 Total 105 33 0 138 4. Specific Scheme Monitoring Issues and Completions
76% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
4.1.1 There was one addition to the departmental programme in Quarter 3, £173,000 for a solar panel scheme at Gun Wharf.
4.1.2 All schemes are currently forecast to breakeven, except for the Better for Less related schemes which are forecasting an underspend of £70,000 pending member decision on the next stage of delivery of transformation in 2014/15 onwards.
4.2Children and Adults
4.2.1 The 2013-14 capital budget reported to Cabinet on 11 February 2014 was £41.8 million which included the addition of over £10.0 million of Targeted Basic Need Grant. This was the subject of a successful bid to fund the New Horizons Primary Academy in Chatham, additional capacity in the relocated Abbey Court School and the expansion of Danecourt School.
4.2.2 The capital monitoring includes a standing item to update Members on the progress of the Council’s Academies programme:
Strood Academy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring 2013/14Report | 169 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.