127/2014 The Cabinet recommended to Council the approval of the additional works to redevelopment to the capital programme, with funding of £1.4m to be funded by Prudential Borrowing . Reasons: Approval of funding will allow the redevelopment of to proceed, with the award of the contract for the substantive development works.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
To seek permission for an additional £1.4m funding to be added to the capital programme in order to proceed with the proposed redevelopment of Strood Sports Centre.
1. Budget and Policy Framework
1.1In accordance with the Constitution, additions to the Capital Programme are a matter for Council, following recommendations from Cabinet.
1.2The sports centre development forms part of a wider Council ambition to improve facilities in Strood, which also includes the provision of a new Community Hub. The development is part of the Medway Sporting Legacy plan, which was launched in July 2013, and is consistent with the Council Plan 2013 - 2015.
1.3The scheme will be financed through Prudential Borrowing, funded by additional revenue generated by the enhanced facilities.
Background
2.1In March 2013 Procurement Board approved a Gateway 1 report for the £1.9m refurbishment of Strood Sports Centre, and since the summer of 2013 a project team has been developing proposals for its redevelopment.
2.2These proposals include: more than doubling the footprint of the existing fitness suite creating three new dance/aerobics studios creating a new cycle spin room redesigning the café and reception areas improving the visual appearance of the entrance and frontage. 2.3 Participation levels at the centre for 2013/2014 are circa 330,000, a figure that is likely to grow considerably upon completion of the redevelopment.
2.4As a comparison, the participation levels at Medway Park have increased by 240,000 in two years since the completion of the refurbishment and improvement works carried out at that site from a figure of 540,000 in 2011 to 780,000 last year. The increased participation levels at Medway Park have also generated increased income, primarily through a rise in the number of memberships. It is on this basis that a 15-year Prudential Borrowing business plan underpinned the Gateway 1 report on Strood Sports Centre.
2.5When developing the programme, a key consideration has been the need to complete the new fitness suite in time for January 2015, as the first three months of the calendar year generate the most income for new membership sign-ups.
2.6In order to achieve this key date, the overall programme has been developed on a phased basis, and a programme of enabling works has now been completed. This enables the substantive redevelopment works to be undertaken while ensuring the centre remains open at all times with minimal impact. In addition, planning permission has been sought and approved for the improvements to the centre’s entrance and frontage.
2.7In April 2014 Council approved the addition of the Strood Sports Centre redevelopment to the capital programme with funding of £500,000 at that stage, pending Gateway 3 approval of the substantive works.
2.8Gateway 3 approval was granted at Procurement Board on 19 June 2014. The successful tender means the original budget projection of £1.9m is still robust.
3. Advice and analysis
3.1Approval of the additional £1.4m funding for the project will allow the contract for the substantive works to be issued, following Gateway 3 approval from Procurement Board. This is in line with approval given at Gateway 1 to progress a scheme for Strood Sports Centre, based on £1.9m Prudential Borrowing.
3.2Redevelopment of the centre will create a facility that reflects the needs of customers and provides opportunities to increase revenues helping to make the operation of Medway Council sports centres more cost effective. 4. Risk management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.