132/2014 The Cabinet agreed that this Gateway 1 high risk report progress to Gateway 2 of the procurement process and tenders for the extension and remodelling of Danecourt School be invited. Reasons: The new accommodation is required to enable an additional 40 spaces to be available from September 2015.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
CABINET 15 JULY 2014 GATEWAY 1 PROCUREMENT COMMENCEMENT: DANECOURT COMMUNITY SPECIAL SCHOOL - EXPANSION WORKS Portfolio Holder: Councillor O’Brien, Children’s Services (Lead Member)
Report from: Barbara Peacock, Director of Children and Adult Services
Author: Debbie Wright, Category Lead Chris Sewell, Project Support Officer SUMMARY
This report seeks approval for the commencement of the procurement process for the expansion works at Danecourt Community Special School to enable an increase in the number of pupils and an extension to the range of SEN designations.
This Gateway 1 report has been approved for submission to Cabinet after review and discussion at the Children and Adults Directorate Management Team Meeting on 10 June 2014 and Procurement Board on 18 June 2014.
The Children & Adults Directorate Management Team has recommended that this project be approved as a Category B High Risk project at Gateway 1 by the Procurement Board. Under the Council’s constitution, the decision to commence procurement is therefore a decision for Cabinet.
1. Budget & Policy Framework
1.1The award of this contract, which will be undertaken in accordance with the Council’s procurement procedures will support Medway Council’s published strategy document “Special Educational Needs – An Inclusive policy and strategy for Medway 2009 – 2014”. This sets out the ambition that wherever possible the special educational needs of Medway children should be met so that they are able to learn and achieve in local provision.
1.2The budget framework for this procurement process is set out in the Exempt Appendix. 2. Background
2.1Medway has agreed the principle that the trend to place children out of area or in independent provision should be reversed where possible and aims to educate as many children as possible close to where they live and to reduce the number of children and young people being educated outside of mainstream or local maintained special schools.
2.2Danecourt Community Special School is an outstanding school for pupils aged 4-11 with moderate learning difficulties (MLD) and complex autistic spectrum disorders (ASD). In recent years the needs of new pupils attending Danecourt have become more complex, and in reality many pupils have very complex MLD (bordering/crossing over to severe learning difficulties (SLD)).
2.3The school was originally built in the 1950s and over time additional spaces have been added to accommodate additional pupils. There are constraints with the size of the overall accommodation and specific spaces, for example the hall and staff areas.
2.4Pupils at Danecourt achieve well and make very good progress. The school has been judged ‘Outstanding’ at the last inspection in October 2012. In recent years there has been a significant growth in the number of primary age pupils with MLD (80% growth in 4 years) and ASD (88% growth in 4 years) and we expect numbers to continue to rise. Danecourt is in most cases the only school in Medway able to meet these needs.
Funding/Engagement From External Sources
2.540 additional places must be provided prior to September 2015 using funding of £1.31m from the Education Funding Agency.
3. PROCUREMENT DEPENDENCIES & OBLIGATIONS
3.1Project Dependency
None
3.2Statutory/Legal Obligations
The budgeted value of this procurement is below EU procurement Regulations. 4. BUSINESS CASE
4.1Procurement Project Outputs / Outcomes
As part of the successful delivery of this procurement requirement, the following procurement project outputs / outcomes within the table below have been identified as key and will be monitored as part of the procurement project delivery process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.