133/2014 The Cabinet noted the positive performance of the contract during its first year and agree to a Gateway 5 report being submitted at the next anniversary of the contract in 2015. Reasons: The contract continues to meet the aims and objectives set out by Medway Council as outlined in the Gateway 3 report and has delivered to the quality and financial requirements of the contract.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report sets out a review of the progress of the contract currently delivered through the supplier(s) as highlighted within paragraph 1.1 of this report.
This Gateway 4 Report has been approved for submission to the Cabinet after review and discussion at Children and Adults Directorate Management Team meeting on 10 June 2014 and Procurement Board on 18 June 2014.
1. BACKGROUND INFORMATION
1.1Contract Background Information
1.1.1 From 31 March 2013 the law was changed to abolish discretionary elements of the Social Fund, namely Community Care Grants and Crisis Loans. Some funding was then transferred to Local Authorities to use as they saw fit to meet local needs by way of Local Welfare Provision.
1.1.2 A contract was awarded to West Kent Extra for the delivery of Medway’s Local Welfare Provision. This provision (LWP) operates as a grant and not as a loan scheme. This ensures that money is spent on the items needed and claimants in a crisis situation are provided with a solution which is not in a monetary form but satisfies the need i.e. food, clothing, household goods etc.
1.1.3 This funding supports vulnerable people in Medway who: Are in a crisis due to a disaster or other emergency
Need support to regain independence after a period of institutional care Need support to regain a more settled way of life Are at risk of losing their independence or ending up in institutional care
1.1.4 The contract duration is between 1 August 2013 and 31 March 2015 with provision to extend the contract for a period of 2 years subject to availability of further funding from Central Government.
1.2Funding/Engagement From External Sources
1.2.1 As part of the Welfare Reform Act 2012, the Discretionary Social Fund scheme administered by the Department of Works and Pensions (DWP) was abolished on the 1 April 2013. The responsibility for part of this discretionary scheme transferred to all Local Authorities to develop Local Welfare Provision Schemes. The funding level identified was for a period of 2 years. It is unclear what the longer term intentions are nationally for Local Welfare Provision Schemes, but Central Government has indicated that funding may not continue post-March 2015.
2. STATUTORY/LEGAL OBLIGATIONS
2.1Statutory/Legal Obligations
2.1.1 Section 70 Welfare Reform Act 2012 repealed the statutory provisions relating to community care grants and crisis loans.
2.1.2 There are no statutory requirements for the provision of the Medway Local Welfare Provision (LWP) Scheme. However the service has implications and impacts on other local authority functions including:
Impact on the lives of local vulnerable people in the event of an emergency or crisis. Pressure and strain on existing local services and local partners. 3. BUSINESS CASE
3.1Procurement Project Outputs / Outcomes
The following procurement outcomes/outputs identified as important at Gateway 1 to the delivery of this procurement requirement and identified as justification for awarding the contract at Gateway 3, have been appraised in the table below to demonstrate how the procurement contract and corresponding supplier(s) has delivered said outcomes/outputs.
Outputs / How will success Who will measure When will success be How has contract award delivered Outcomes be measured? success of measured? outputs/outcomes? outputs/ outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.