Capital Budget 2014/15 Monitoring 2014/15 - Round 1
NotedScrutiny6 papers
Business Support Overview and Scrutiny Committee noted this item on Tuesday 7 October 2014. Below is the council's own wording, with the papers it was decided on.
The Committee: (a) noted the spending forecasts summarised at Table 1 of the report and the following virements, in accordance with the Council’s delegated financial limits: · the transfer £212,000 from the Basic Need Programme to fund the forecast overspends against the Wainscott Primary and Napier Primary schemes; · the transfer of £451,000 from the Basic Need Programme to the Academies Programme to part fund the cost of asbestos removal; · the transfer £165,000 from the Basic Needs Programme (funded from the Targeted Basic Needs Grant) to fund the overspend on the New Horizons project. (b) noted the recommendation to Council that the following additions to the capital programme, both of which are to be funded through virements from the Adult Social Care Transformation budget: · the transfer £400,000 from Adult Social Care Transformation to fund the Smarter Working @ Gun Wharf project; · the transfer £120,000 from Adult Social Care Transformation to fund the construction of additional provision on the Old Vicarage site (c) agreed that information be provided to Councillor Juby with regard to the £35,000 overspend in relation to Napier Primary project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Report to Business Support Overview and Scrutiny Committee
Background
2.1The approved capital programme for 2014/15 and future years is £83.8 million, being £56 million in respect of brought forward schemes and £27.8 million in respect of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendices. The accompanying narrative provides a brief description of each scheme, describing the progress of each and the outputs achieved. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate, with narrative from the project managers providing a more detailed explanation of the progress of each scheme against its plan. Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2014 Approved
Spend to
Forecast Variance 2014-15 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,855 31,180 2,070 1,606 0 Department Children and 163,042 128,885 30,046 4,955 843 Adult Services Regeneration, Community and 112,001 66,637 26,207 19,156 0 Culture Member Priorities 837 247 575 0 (15) TOTAL 310,735 226,949 58,897 25,718 828
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 8 4 0 12 Children & Adults 53 5 1 59 RCC 57 0 0 57 Member Priorities 10 1 0 11 Total 125 13 1 139 4. Specific Scheme Monitoring Issues and Completions
86% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support (Appendix 2)
4.1.1 Council has agreed an addition to the Business Support Department’s capital programme for 2014-2015. This is an increase of £185,000 in respect of the relocation of Children’s Services to Broadside, MHS headquarters, and work to be undertaken at Eagle Court to transform it into a conference facility. A further £475,000 has also been added to the Mercury Abatement scheme. £3.02 million was rolled forward from the 2013/14 programme, giving the Department a total capital programme of £3.68 million this year.
4.1.2 The Department’s forecast reflects the planned phasing of expenditure and anticipates a roll forward of £1.61 million into future years.
4.1.3 The Cabinet on 30 September 2014 is being asked to approve a £400,000 addition to the capital programme to take forward the Smarter Working @ Gun Wharf project. This would be funded through a virement from the non- ringfenced Adult Social Care Capital Grant.
4.2Children and Adults (Appendix 3)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.