Resolved
The Committee agreed to note the spending forecasts summarised in Table 1 and also that Cabinet has recommended to Council the addition to the programme outlined at paragraph 4.4 of the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 1 December 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the spending forecasts summarised in Table 1 and also that Cabinet has recommended to Council the addition to the programme outlined at paragraph 4.4 of the report.
This report presents the quarter 2 capital monitoring forecasts for 2016/2017.
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that expenditure for each capital scheme remains within the budget approved by the Council, but it remains the responsibility of Council to approve schemes for inclusion in the capital programme.
1.2This Committee has responsibility for the regular monitoring of budgets and the capital programme
2.1The approved capital programme for 2016/17 and future years, is £110.5m, being £86.0m of brought forward schemes and £24.5m of new approvals.
2.2This report consolidates the capital expenditure forecasts prepared by each directorate. Appendix 1 gives the full detail by project and the notes in section 3 and 4 of this report represent a commentary on areas of concern or items of particular interest.
3. Summary of the Capital Programme 2016/2017
3.1Table 1 summarises the overall capital programme and the latest forecast position, whilst Table 2 indicates how the current programme is funded. Table 1: Quarter 2 Monitoring Summary Current 2016/17 2017/18 2018/19 2019/20 Forecast Budget Forecast Forecast Forecast Forecast Variance £000s £000s £000s £000s £000s £000s Children and Adults 32,927 22,972 8,300 1,635 0 (20) Regeneration, Community, Environment and Transformation 59,338 25,082 24,236 10,619 317 916
Business Support Department 3,197 2,573 475 148 0 (1) Housing Revenue Account 14,709 8,288 6,421 0 0 0 Member Priorities 301 238 40 0 0 (23) Public Health 0 0 0 0 0 0 TOTAL 110,471 59,153 39,472 12,403 317 874
Table 2: Summary of Capital Funding Member Total Funding Source C&A RCET HRA BSD PH Priorities Programme
£000s £000s £000s £000s £000s £000s £000s Borrowing 0 12,237 1,323 298 0 0 13,858 Capital Grants 18,892 41,126 36 903 0 0 60,957 Capital Receipts 0 2,589 1,002 0 0 301 3,892 RTB Receipts 0 378 0 0 0 0 378 S106 Contributions 11,220 2,546 0 0 0 0 13,766 Revenue / Reserves 2,815 461 836 13,508 0 0 17,620 TOTAL 32,927 59,338 3,197 14,709 0 301 110,471
3.2In spite of its scale and complexity, the programme is generally on time and to budget, with very few issues to report. The position on Rochester Riverside and the multi-storey car park is outlined in paragraphs 4.4 and 4.5.
4. New Schemes and Virements
4.1Following the 2016/17 local government settlement and after Council had agreed the capital programme, the DfE announced the 2018/19 Basic Need allocations and this grant worth £3.111m has been added to the programme in quarter 2.
4.2At its meeting on 13 October, the Council agreed to add £311,000 of schemes to be funded from Section 106 receipts. The addition to the cost of works at the Crematorium will be included in the quarter 3 figures. Council also agreed six new School projects funded from the Basic Need Grant.
4.3At its meeting on 21 July, the Council agreed £226,000 under prudential borrowing to fund investment in ICT infrastructure.
4.4Whilst some of the Rochester Riverside project costs have been met from the funds made available by the HCA, it has always been the case that the majority of the costs would be funded from borrowing in lieu of later capital receipts as the development progresses. Expenditure in the current financial year is forecast to be around £430,000 and Cabinet has been asked to recommend that Council agree this addition to the programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring detailsAppendix 1 | 175 KB | Download |
PDF |
Rochester Station Multi Storey Car Park: summary of costsAppendix 2 | 177 KB | Download |
PDF |
Capital Budget Monitoring 2016/17 Quarter 2Report | 142 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.